RERA: A51800043517

Arkade Serene

by Arkade Developers Private Limited Company
Certificate Signed P51800029961
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51800029961
Registration No.
REA51800086108
Registration Date
2021-07-18
Developer
Arkade Developers Private Limited Company
Architect
Kalakruti Architects & Planners
Project Bank
HDFC BANK
Proposed Possession
2024-06-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
2748.70 sq.m
Total FSI
7420.67
Approved FSI
3458.78
MahaRERA QR
Arkade Serene
MahaRERA — P51800029961
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors25
Sanctioned25
⬇️Basements1
🅿️Closed Parking122
📅Completion2024-06-30

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 38.0 0 0 0
0%
2Bhk 56.119998931884766 0 0 0
0%
2Bhk 59.150001525878906 0 0 0
0%
2Bhk 65.19999694824219 0 0 0
0%

Arkade Serene

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 38.0 21 21 0
100%
2 BHK 56.12 59 52 7
88%
2 BHK 59.15 21 21 0
100%
2 BHK 65.2 21 21 0
100%

Construction Progress

Arkade Serene

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.73%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate57%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.57%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises91%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises91%
Overall Percentage of Completion of the work done For the entire Building /Wing72%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.99%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks99%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing73%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 90%
Energy management
Fire Protection And Fire Safety Requirements 75%
Fitness Center and Society Office 50%
Landscaping & Tree Planting 15%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 50%
Solid Waste Management And Disposal 85%
Storm Water Drains 50%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply 50%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.