RERA: A51800043517

ASCEND TOWER

by M. MAMTORA ASSOCIATES Partnership
Certificate Signed P51800049273
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51800049273
Registration No.
REA51800127973
Registration Date
2023-02-03
Developer
M. MAMTORA ASSOCIATES Partnership
Architect
Sanjay B Shah
Project Bank
KOTAK MAHINDRA BANK LIMITED
Proposed Possession
2026-06-05
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
184
Units Sold
21 (11%)
Buildings
2
Project Area
3274.60 sq.m
Total FSI
8841.42
Approved FSI
7817.42
MahaRERA QR
ASCEND TOWER
MahaRERA — P51800049273
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors22
Sanctioned22
🏠Habitable19
🔢Total Units74
🏡Residential74
🅿️Closed Parking1
📅Completion2026-05-06
🏗️Proposed Floors22
Sanctioned22
🏠Habitable19
🔢Total Units110
🏡Residential110
🅿️Closed Parking1
📅Completion2026-05-06

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 35.2599983215332 0 0 0
0%
1Bhk 36.59000015258789 0 0 0
0%
1Bhk 36.970001220703125 0 0 0
0%
1Bhk 37.220001220703125 0 0 0
0%
2Bhk 41.869998931884766 0 0 0
0%
2Bhk 41.91999816894531 0 0 0
0%
2Bhk 44.720001220703125 0 0 0
0%
2Bhk 50.81999969482422 0 0 0
0%
2Bhk 52.029998779296875 0 0 0
0%
3Bhk 59.209999084472656 0 0 0
0%
3Bhk 64.19000244140625 0 0 0
0%
3Bhk 69.2699966430664 0 0 0
0%

Ascend Tower A Wing

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 36.59 19 0 19
0%
2 BHK 41.83 6 6 0
100%
2 BHK 41.84 19 18 1
95%
2 BHK 50.8 11 10 1
91%
3 BHK 59.18 4 3 1
75%
3 BHK 64.19 15 5 10
33%

Ascend Tower B Wing

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 34.9 19 2 17
11%
1 BHK 36.97 19 3 16
16%
1 BHK 37.1 36 6 30
17%
2 BHK 44.58 31 29 2
94%
2 BHK 52.0 5 1 4
20%

Construction Progress

ASCEND TOWER A WING

Basement (if any)0%

Ascend Tower A Wing

Excavation95%

ASCEND TOWER A WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.28%

Ascend Tower A Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

ASCEND TOWER A WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.4%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%

Ascend Tower A Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises2%

ASCEND TOWER A WING

Plinth100%
Podiums (if any) 80%

Ascend Tower A Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

ASCEND TOWER A WING

Sanitary Fittings within the flats / premises5%
Slabs of Super Structure75%

Ascend Tower A Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.23%

ASCEND TOWER A WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks26%

Ascend Tower A Wing

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing2%
X number of Basement(s) and Plinth90%
X number of Podiums80%
X number of Slabs of Super Structure30%

ASCEND TOWER B WING

Basement (if any)0%

Ascend Tower B Wing

Excavation95%

ASCEND TOWER B WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.28%

Ascend Tower B Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

ASCEND TOWER B WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.4%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises17%

Ascend Tower B Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises2%

ASCEND TOWER B WING

Plinth100%
Podiums (if any) 80%

Ascend Tower B Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

ASCEND TOWER B WING

Sanitary Fittings within the flats / premises5%
Slabs of Super Structure70%

Ascend Tower B Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.23%

ASCEND TOWER B WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks26%

Ascend Tower B Wing

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing2%
X number of Basement(s) and Plinth90%
X number of Podiums80%
X number of Slabs of Super Structure30%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.