RERA: A51800043517

Avd Residencia

by Avd Infrastructure Partnership
Certificate SignedP51800017156

Project Information

RERA Certificate No.
P51800017156
Registration No.
REA51800040512
Registration Date
2021-09-09
Developer
Avd Infrastructure Partnership
Architect
Creative Consultant Anddesigners
Proposed Possession
2023-03-30
Revised Possession
1900-01-01
Extended Possession
2024-09-30
Units Sold
0
Buildings
1
Project Area
389.60 sq.m
Total FSI
1466.20
Approved FSI
1245.20
MahaRERA QR
Avd Residencia
MahaRERA — P51800017156
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors11
Sanctioned11
⬇️Basements1
🅿️Closed Parking1
📅Completion2022-03-31

Apartment Configurations

Avd Residencia

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK33.81202
0%
1 BHK34.09440
100%
1RK23.08101
0%
2 BHK49.42541
80%
2 BHK49.55303
0%
Add. Tenant Area15.74110
100%
Shop78.0110
100%

Construction Progress

AVD RESIDENCIA

Basement (if any)100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Avd Residencia

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station75%
Energy management
Fire Protection And Fire Safety Requirements75%
Landscaping & Tree Planting50%
Open Parking
SOCIETY OFFICE100%
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains75%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting75%
Water Supply75%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.