Project Information
RERA Certificate No.
P51800076741
Registration No.
REA51800150438
Registration Date
2024-06-27
Developer
Kalindi Estate Developers Others
Architect
Rakesh G Waghmare G WAGHMARE
Project Bank
AXIS BANK
Proposed Possession
2027-04-30
Total Units
52
Units Sold
0 (0%)
Buildings
1
Project Area
6692.05 sq.m
Total FSI
25997.00
Approved FSI
14169.40
Building No.9 - Phase Ii
MahaRERA — P51800076741
MahaRERA — P51800076741
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors22
✅Sanctioned22
🏠Habitable21
🔢Total
Units52
🏡Residential52
Apartment Configurations
BUILDING NO 9 WING A Wing B
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 2BHK | 84.95 | 9 | 0 | 9 | 0% |
| 2BHK | 86.16 | 9 | 0 | 9 | 0% |
| 3BHK | 113.54 | 9 | 0 | 9 | 0% |
| 3BHK | 113.76 | 9 | 0 | 9 | 0% |
| 3BHK | 116.02 | 8 | 0 | 8 | 0% |
| 3BHK | 116.28 | 8 | 0 | 8 | 0% |
| Existing Tenant 2BHK | 96.24 | 3 | 0 | 3 | 0% |
| Existing Tenant 2BHK | 96.28 | 21 | 0 | 21 | 0% |
| Existing Tenant 2BHK | 98.47 | 1 | 0 | 1 | 0% |
| Existing Tenant 3BHK | 122.67 | 1 | 0 | 1 | 0% |
| Existing Tenant 3BHK | 125.97 | 2 | 0 | 2 | 0% |
| Existing Tenant 3BHK | 126.0 | 1 | 0 | 1 | 0% |
| Existing Tenant 3BHK | 126.02 | 17 | 0 | 17 | 0% |
| Existing Tenant 3BHK | 133.4 | 3 | 0 | 3 | 0% |
| Existing Tenant 3BHK | 133.45 | 10 | 0 | 10 | 0% |
| Existing Tenant 3BHK | 133.46 | 10 | 0 | 10 | 0% |
| Existing Tenant 3BHK | 151.22 | 1 | 0 | 1 | 0% |
| Office space | 26.22 | 1 | 0 | 1 | 0% |
| Office space | 31.93 | 1 | 0 | 1 | 0% |
| Office space | 90.35 | 1 | 0 | 1 | 0% |
| Office space | 94.36 | 1 | 0 | 1 | 0% |
| Office space | 123.12 | 1 | 0 | 1 | 0% |
| Office space | 126.78 | 1 | 0 | 1 | 0% |
Construction Progress
BUILDING NO 9 WING A Wing B
RERA Registered Amenities
✅Aggregate area of recreational Open Space100%
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station70%
✅Energy managemcnt
✅Fire protection and fire safety requirements
✅Internal Roads & Footpaths100%
✅Landscaping & Tree Planting
✅Open Parking100%
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
✅Solid Waste Management And Disposal
✅Storm Water Drains100%
✅Street Lighting100%
✅Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply50%
✅Water conservation /Rain water harvesting