Century Vista by Shreeji Infra

πŸ“ Sector-27, Raigarh Β· 410210
131
Units
2029
Possession
1
Buildings
Certificate Signed
Status
01

Possession Timeline

Proposed
Dec 2029
Status
New
02

Unit Configurations (per MahaRERA)

03

RERA Trust Record

MahaRERA No.
P52000079575
Registered
2025-03-17
Litigation
None on record
Escrow Bank
ICICI BANK LIMITED
Architect
Vastospati Design Group
Total FSI
10390
04

Buildings Β· 1 Wing(s)

CENTURY VISTA34 floors Β· 131 units
05

Land DNA Β· Genesis

Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06

Location

πŸ“ Sector-27
0.000000000000000,0.000000000000000
β–Έ Explore map & Street View β€” for verified buyers
07

Promoter & Professionals

AVCHAR PANCHA DEVDAPartner
ISHWAR VIRJI PATELPartner
Karthik Mahadev PatelPartner
Mahesh Shankar MatePartner
09

Construction Progress

9% avg
Excavation100%
Basement (if any)0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 0%
12

Floor Plans, E-Brochure & Payment Plans

πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13

EMI Calculator

β€”
14

More by Shreeji Infra

Shreeji NakshatraMalad West Β· Under ConstructionShreeji Sai DivineKandivali West Β· Under ConstructionShreejee MrugarchanaMulund West Β· Ready PossessionShreeji EternityMalad West Β· Under ConstructionShreeji DivineKharghar Β· Under ConstructionShreeji BlissMalad West Β· Sold Out
15

MahaRERA projects nearby in Sector-27

ELYSIAN
?

Frequently Asked Questions

When is possession of CENTURY VISTA?

As per MahaRERA, proposed possession is Dec 2029.

Is CENTURY VISTA RERA-registered?

Yes β€” MahaRERA registration P52000079575, registered 2025-03-17. No litigations on record.

Who is the developer?

Shreeji Infra β€” 35 projects tracked on Mumbai Property Exchange. View their track record β–Έ

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Sector-27 β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
Our advisor replies on WhatsApp within 2 working hours (9am–8pm IST).
β˜… Featured
Shapoorji Pallonji Real Estate
Aquila, Kandivali East
3 BHK Β· β‚Ή45,268/sq.ft Β· Possession Mar 2028
Learn more β€Ί

πŸ“° Latest Mumbai Property News

View all news β†’