Kishor Kunj by Bhagwati Builders And Developers

πŸ“ Vasai, Palghar Β· 401202
22
Units
2017
Possession
1
Buildings
Certificate Signed
Status
01

Possession Timeline

Proposed
Dec 2017
Revised
Dec 2017
Status
Ongoing
02

Unit Configurations (per MahaRERA)

ConfigurationCarpetIndicative Price
Residential6,523 ftΒ²On request
Configurations & carpet per MahaRERA filing Β· indicative price = locality rate Γ— carpet (not the developer's quote).
πŸ’¬ Live availability, floor plans & today's price β€” on WhatsApp
03

RERA Trust Record

MahaRERA No.
P99000006836
Registered
2017-08-16
Litigation
None on record
Escrow Bank
β€”
Architect
Umesh Kekre
Total FSI
866
04

Buildings Β· 1 Wing(s)

Kishor Kunj11 floors Β· β€” units
05

Land DNA Β· Genesis

Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06

Location

πŸ“ Vasai
19.387277999999998,72.828140000000005
β–Έ Explore map & Street View β€” for verified buyers
07

Promoter & Professionals

DAMJI NANJI BHANUHSALIPartner
DINESH DAMJI BHANUSHALIPartner
KISHOR DAMJI BHANUSHALIPartner
09

Construction Progress

100% avg
Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Plinth100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
10

Amenities

Electrical Meter Room, Sub-Station, Receiving StationLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And DisposalStorm Water DrainsWater Conservation, Rain water HarvestingWater Supply
12

Floor Plans, E-Brochure & Payment Plans

πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13

EMI Calculator

β€”
08

Property Rates in Vasai

Residential Β· Sale
β‚Ή10,000–45,000/sqft
Commercial Β· Sale
β‚Ή6,500–15,000/sqft
2 BHK Β· Rent
β‚Ή20,000–45,000/mo
14

More by Bhagwati Builders And Developers

New Palm BeachAiroli Β· Under ConstructionBhagwati Kharghar Phase IIKharghar Β· Sold OutBhagwati KhargharKharghar Β· Sold OutBhagwati GreensKharghar Β· Sold OutBhagwati EleganzaGhansoli Β· Sold OutBhagwati ImperiaUlwe Β· Sold Out
15

MahaRERA projects nearby in Vasai

MLDC YASHWANT ORCHID PHASE I923 unitsMAYFAIR VIRAR GARDENS BUILDING NO 17, 18, 19, 23A, 26, 27901 unitsPEARL GARDENS656 unitsNakshatra Veda II514 unitsSunteck Beach Residences 4470 unitsSHRIPAL SATTVA - BLDG. 1431 unitsAkhand Phase 2409 unitsVIMAL CLASSIC380 unitsARMAAN LOTUS375 unitsOLYMPUS TOWERS355 unitsNAKSHATRA NIRVAANA II343 unitsNakshatra Veda340 units
?

Frequently Asked Questions

When is possession of KISHOR KUNJ?

As per MahaRERA, proposed possession is Dec 2017, revised to Dec 2017.

Is KISHOR KUNJ RERA-registered?

Yes β€” MahaRERA registration P99000006836, registered 2017-08-16. No litigations on record.

Who is the developer?

Bhagwati Builders And Developers β€” 11 projects tracked on Mumbai Property Exchange. View their track record β–Έ

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Vasai β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
Our advisor replies on WhatsApp within 2 working hours (9am–8pm IST).
βœ“ MahaRERA PM1330002500505β˜… Featured
Raheja Universal Ltd
SYNOVA (Raheja Tesla-3), Juinagar
β‚Ή23,702/sq.ft
Learn more β€Ί