35
Units
2025
Possession
1
Buildings
Certificate Signed
Status
01

Possession Timeline

Proposed
Oct 2025
Status
New
02

Unit Configurations (per MahaRERA)

ConfigurationCarpetIndicative Price
1 BHK225–381 ftΒ²On request
Configurations & carpet per MahaRERA filing Β· indicative price = locality rate Γ— carpet (not the developer's quote).
πŸ’¬ Live availability, floor plans & today's price β€” on WhatsApp
03

RERA Trust Record

MahaRERA No.
P99000047521
Registered
2022-11-07
Litigation
None on record
Escrow Bank
HDFC BANK
Architect
Sanat Mehta & Associates
Total FSI
1541
04

Buildings Β· 1 Wing(s)

Maruti Complex Wing F5 floors Β· β€” units
05

Land DNA Β· Genesis

Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06

Location

πŸ“ Nalasopara
0.000000000000000,0.000000000000000
β–Έ Explore map & Street View β€” for verified buyers
07

Promoter & Professionals

Amit VairagdePartner
Dharmendra KhodaPartner
Dnuaneshwar PatilPartner
Hardik RautPartner
Hemanshu KapadiaPartner
09

Construction Progress

0% avg
Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Plinth0%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
10

Amenities

Aggregate area of recreational Open SpaceElectrical Meter Room, Sub-Station, Receiving StationLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And DisposalStorm Water DrainsWater Conservation, Rain water HarvestingWater Supply
12

Floor Plans, E-Brochure & Payment Plans

πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13

EMI Calculator

β€”
14

More by Om Sai Developers

Kavya AshwameghGhatkopar East Β· Under ConstructionAxiom GloriaMulund West Β· Under ConstructionAxiom VrindavanMulund West Β· Under ConstructionAxiom VrikshMalad West Β· Under ConstructionAxiom GurubhaktiMulund East Β· Under ConstructionSiddhivinayak AnayaDronagiri Β· Under Construction
15

MahaRERA projects nearby in Nalasopara

ARMAAN LOTUS375 unitsOAKWOOD PHASE-2206 unitsANAND HEIGHT WING BAND C196 unitsDhananjay Grand Avenue112 unitsJB PEARL56 unitsSHRI OMKAR AND OMKARNARAYAN CHS LTD1 unitsSHREE KRUSHNA ARCADEF CLOCK TOWER PHASE 1MANIBHADRA HEIGHTSVEER SPLENDORSERENITY GARDENS WING E AND FELITE HOMES
?

Frequently Asked Questions

When is possession of Maruti Complex?

As per MahaRERA, proposed possession is Oct 2025.

Is Maruti Complex RERA-registered?

Yes β€” MahaRERA registration P99000047521, registered 2022-11-07. No litigations on record.

Who is the developer?

Om Sai Developers β€” 662 projects tracked on Mumbai Property Exchange. View their track record β–Έ

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Nalasopara β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
Our advisor replies on WhatsApp within 2 working hours (9am–8pm IST).
βœ“ MahaRERA P52000016540β˜… Featured
The Wadhwa Group
Wadhwa Wise City, New Panvel
1 BHK, 2 BHK, 3 BHK Β· β‚Ή16,946/sq.ft Β· Possession 2026-12-01 00:00:00
Learn more β€Ί

πŸ“° Latest Mumbai Property News

View all news β†’