01
Possession Timeline
Proposed
Dec 2021
Revised
Dec 2021
Status
Ongoing
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
1 RK352 ft²On request
2 RK423 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P51700011727
Registered
2017-08-31
Litigation
No reported in source
Escrow Bank
—
Architect
—
Total FSI
—
04
Buildings · 2 Wing(s)
Girjatmak A4— floors · — units
Mahaganapati A3— floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Mumbai
19.243047900000001,73.179212500000006
19.243047900000001,73.179212500000006
▸ Explore map & Street View — for verified buyers
09
Construction Progress
37% avgExcavation100%
Stilt Floor100%
X number of Basement(s) and Plinth100%
X number of Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.80%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises25%
Overall Percentage of Completion of the work done For the entire Building /Wing10%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
10
Amenities
Aggregate area of recreational Open SpaceElectrical Meter Room, Sub-Station, Receiving StationLandscaping & Tree PlantingSewerage (Chamber, Lines, Septic Tank , STP)Street LightingWater Conservation, Rain water HarvestingWater Supply
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory09
Resale Flats for Sale in Mumbai
410
Flats for Rent in Mumbai
213
Commercial Projects in Mumbai
14
More by Siddhivinayak Builders And Developers
15
MahaRERA projects nearby in Mumbai
The Royal Bay579 unitsDream Ikon477 unitsGodrej Reserve Wing 3371 unitsLa Mer One Phase - II346 unitsParadise C H S Ltd341 unitsDaffodil Heights326 unitsGodrej Reserve Wing 2308 unitsNms Midas308 unitsNeelkanth Palm Avenue301 unitsPearl Blossom291 unitsGodrej Varanya Phase 1282 unitsAniraj Tower Chs Ltd274 units
?
Frequently Asked Questions
When is possession of Moreshwar Nagar II?
As per MahaRERA, proposed possession is Dec 2021, revised to Dec 2021.
Is Moreshwar Nagar II RERA-registered?
Yes — MahaRERA registration P51700011727, registered 2017-08-31. The current MahaRERA source record reports no litigations.
Who is the developer?
Siddhivinayak Builders And Developers — 23 projects tracked on Mumbai Property Exchange. View their track record ▸
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.