Project Information

RERA Certificate No.
P51800005753
Registration No.
REA51800015470
Registration Date
2017-08-11
Developer
R B Developers Partnership
Architect
Modi Bhavin Arvind
Project Bank
KOTAK MAHINDRA BANK LIMITED
Proposed Possession
2018-06-30
Revised Possession
2018-06-30
Extended Possession
2022-06-30
Total Units
24
Units Sold
9 (38%)
Buildings
1
Project Area
495.60 sq.m
Total FSI
1625.78
Approved FSI
1625.78
MahaRERA QR
Ossia Enclave
MahaRERA — P51800005753
Scan to verify on MahaRERA portal

Wing-wise Details

šŸ—ļøProposed Floors28
āœ…Sanctioned28
šŸš—Open Parking3
šŸ“…Completion2018-06-30

Apartment Configurations

Ossia Enclave

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK28.79110
100%
1 BHK32.7550
100%
2 BHK54.53770
100%
3 BHK57.6101
0%
3 BHK63.63752
71%
3 BHK64.75624
33%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 Bhk28.790000915527344000
0%
1Bhk32.70000076293945000
0%
2 Bhk54.529998779296875000
0%
3 Bhk57.599998474121094000
0%
3 Bhk63.630001068115234000
0%
3 Bhk64.75000
0%

Construction Progress

OSSIA ENCLAVE

Basement (if any)100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises85%
Slabs of Super Structure70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks65%

Ossia Enclave

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate10%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises90%
Overall Percentage of Completion of the work done For the entire Building /Wing69%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises85%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.65%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing70%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure70%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
āœ…Electrical Meter Room, Sub-Station, Receiving Station60%
āœ…Energy management80%
āœ…Fire Protection And Fire Safety Requirements
āœ…Landscaping & Tree Planting
āœ…Open Parking
āœ…Sewerage (Chamber, Lines, Septic Tank , STP)80%
āœ…Solid Waste Management And Disposal80%
āœ…Storm Water Drains80%
⬜Street Lighting
āœ…Treatment And Disposal Of Sewage And Sullage Water80%
āœ…Water Conservation, Rain water Harvesting80%
āœ…Water Supply80%
CallWhatsApp
āœ‰ļø

Get in Touch

Our team will connect with you shortly

+91
šŸ”’ Your details are secure with us
⚔ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
šŸ‘‹ Looking for the right project? Let me help you find it!
šŸ—ļø
MPE Project Advisor
ā— Online now