✓ MahaRERA P51800052475RERA: no litigation reportedS S Vellozia CHS
Shree S S Infra Developers
📍 Bhandup West, Mumbai Suburban · 400078
212
Units
2028
Possession
2
Buildings
Kept in Abeyance
Status
Lifecycle requires verification
Ask an advisor to verify the current project and inventory status.
Source stage: New Project · mapped resale: 0 · mapped rental: 0 · primary status: not confirmed
01
Possession Timeline
Proposed
Dec 2028
Status
New Project
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
1 RK300 ft²On request
Shop136–336 ft²On request
1 BHK388–396 ft²On request
2 BHK523–562 ft²On request
Office Space254–603 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P51800052475
Registered
—
Litigation
No reported in source
Escrow Bank
DNS Bank
Architect
—
Total FSI
6596
04
Buildings · 2 Wing(s)
Sale Building 2- B Wing— floors · — units
Sale Building 2-A Wing— floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Bhandup West
▸ Explore map & Street View — for verified buyers
07
Promoter & Professionals
Shree S S Infra Developers Private LimitedNA
09
Construction Progress
45% avgExcavation100%
Plinth100%
Podiums (if any) 100%
Stilt Floor 100%
Slabs of Super Structure74%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks5%
Basement (if any)0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Sanitary Fittings within the flats / premises0%
10
Amenities
Electrical Meter Room, Sub-Station, Receiving StationSewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsWater Conservation, Rain water HarvestingWater SupplyWater conservation /Rain water harvesting
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory14
More by Shree S S Infra Developers
15
MahaRERA projects nearby in Bhandup West
Shraddha Vardaan723 unitsLaxminarayan Sra Chs Ltd474 unitsPlatinum Heights435 unitsAtlantis389 unitsCorinthia -Tower 1 And Tower 2308 unitsGanesh Bhuvan Chs Ltd303 unitsAshford Regal - Phase I - Wing A Project295 unitsAshford Regal - Phase Ii - Wing B Project295 unitsAniraj Tower Chs Ltd274 unitsVishnu Bhavan Bldg No 4 A Wing Valencia Chs And B Wing Shree Dutt Guru Chs218 unitsAshoka Grandeur205 unitsMarathon Neopark Ashoka Wing A193 units
?
Frequently Asked Questions
When is possession of S S Vellozia CHS?
As per MahaRERA, proposed possession is Dec 2028.
Is S S Vellozia CHS RERA-registered?
Yes — MahaRERA registration P51800052475. The current MahaRERA source record reports no litigations.
Who is the developer?
Shree S S Infra Developers — 269 projects tracked on Mumbai Property Exchange.
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.