Project Information

RERA Certificate No.
P51700013099
Registration No.
REA51700023272
Registration Date
2021-09-09
Developer
M/S Nirman Developers Partnership
Architect
Geo Associates
Project Bank
AXIS BANK
Proposed Possession
2023-12-30
Revised Possession
1900-01-01
Extended Possession
2023-12-30
Total Units
82
Units Sold
12 (15%)
Buildings
2
Project Area
3536.17 sq.m
Total FSI
3138.22
Approved FSI
3138.22
MahaRERA QR
Sahyadri Residency Phase I
MahaRERA — P51700013099
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors6
✅Sanctioned6
🏠Habitable6
🔢Total Units40
🏡Residential38
🏢Non-Residential2
🏗️Proposed Floors9
✅Sanctioned9
🏠Habitable9
🔢Total Units42
🏡Residential42

Apartment Configurations

BUILDING 4

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1RK21.89808
0%
1RK26.36835
38%
1RK26.74835
38%
1RK27.0716610
38%

BUILDING 7/A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK29.38707
0%
1 BHK30.69707
0%
1 BHK31.1707
0%
1 BHK31.39707
0%
1 BHK32.23707
0%
2 BHK46.18707
0%

Construction Progress

BUILDING 4

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises90%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING 7/A

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

✅Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
✅Fire protection and fire safety requirements
✅Internal Roads & Footpaths
✅Landscaping & Tree Planting
✅Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
⬜Solid Waste Management And Disposal
⬜Storm Water Drains
✅Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting

Latest Mumbai Property News