Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Slabs of Super Structure100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
X number of Podiums0%