List PropertyWhatsApp
Best DealsNew Projects๐Ÿ—บ๏ธ Projects MapBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your Property๐Ÿ’ฌ WhatsApp Us
Mumbai property advisory & dataOperating since 1995โœ“ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Shree Sai Arti

by V.K Developers Partnership
Certificate SignedP51900048871
Want us to WhatsApp you? Enter your mobile — we’ll say hello and take it from there.
+91

Project Information

RERA Certificate No.
P51900048871
Registration No.
REA51900121381
Registration Date
2023-01-24
Developer
V.K Developers Partnership
Architect
MR AJAY ADIVEREKAR
Project Bank
CENTRAL BANK OF INDIA
Proposed Possession
2026-12-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
23
Units Sold
6 (26%)
Buildings
1
Project Area
814.38 sq.m
Total FSI
6176.67
Approved FSI
3215.77
MahaRERA QR
Shree Sai Arti
MahaRERA โ€” P51900048871
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors26
โœ…Sanctioned26
๐Ÿ Habitable14
๐Ÿ”ขTotal Units23
๐ŸกResidential23

Apartment Configurations

Shree Sai Arti

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK944.7917017
0%

Construction Progress

SHREE SAI ARTI

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Plinth100%
Podiums (if any)100%
Sanitary Fittings within the flats / premises95%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
Stilt Floor0%

RERA Registered Amenities

โฌœAggregate area of recreational Open Space
โฌœCommunity Buildings
โœ…Electrical meter room, sub-station, receiving station50%
โฌœEnergy managemcnt
โœ…Fire protection and fire safety requirements80%
โฌœInternal Roads & Footpaths
โœ…Landscaping & Tree Planting
โฌœOpen Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)75%
โœ…Solid Waste Management And Disposal
โœ…Storm Water Drains75%
โฌœStreet Lighting
โฌœTreatment And Disposal Of Sewage And Sullage Water
โœ…Water Supply75%
โœ…Water conservation /Rain water harvesting50%