List PropertyWhatsApp
Best DealsNew Projects๐Ÿ—บ๏ธ Projects MapBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your Property๐Ÿ’ฌ WhatsApp Us
Mumbai property advisory & dataOperating since 1995โœ“ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Shree Swami Pushpa Phase-1 Shelar Park

by Shelar Developers Partnership
Certificate SignedP51700011433
Shree Swami Pushpa Phase-1 Shelar ParkProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700011433
Registration No.
REA51700016951
Registration Date
2017-08-31
Developer
Shelar Developers Partnership
Architect
Ramesh S Bhoir
Project Bank
THE KALYAN JANATA SAHAKARI BANK LTD.
Proposed Possession
2023-06-30
Revised Possession
2019-12-31
Extended Possession
2023-06-30
Units Sold
0
Buildings
1
Project Area
745.50 sq.m
Total FSI
2063.71
Approved FSI
2063.71
MahaRERA QR
Shree Swami Pushpa Phase-1 Shelar Park
MahaRERA โ€” P51700011433
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors17
โœ…Sanctioned17

Apartment Configurations

Shree Swami Pushpa

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK38.09330
100%
1 BHK40.713112
85%
2 BHK55.33110
100%
2 BHK57.85981
89%
2 BHK58.5761
86%
2 BHK58.7110
100%

Construction Progress

SHREE SWAMI PUSHPA

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

โœ…Aggregate area of recreational Open Space100%
โฌœCommunity Buildings
โœ…Electrical meter room, sub-station, receiving station100%
โœ…Energy managemcnt100%
โœ…Fire protection and fire safety requirements100%
โœ…Internal Roads & Footpaths100%
โœ…Landscaping & Tree Planting100%
โฌœOpen Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)100%
โฌœSolid Waste Management And Disposal
โœ…Storm Water Drains100%
โฌœStreet Lighting
โฌœTreatment And Disposal Of Sewage And Sullage Water
โœ…Water Supply100%
โœ…Water conservation /Rain water harvesting100%