RERA: A51800043517

Shreeji Eternity Wing - A, Shreeji Eternity Wing - B, Shreeji Eternity Wing - C

by SHREEJI CONSTRUCTION Partnership
Certificate Signed P51800054310
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51800054310
Registration No.
REA51800150029
Registration Date
2024-01-15
Developer
SHREEJI CONSTRUCTION Partnership
Project Bank
HDFC BANK
Proposed Possession
2027-06-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
3
Project Area
3467.63 sq.m
Total FSI
13644.57
Approved FSI
11929.87
MahaRERA QR
Shreeji Eternity Wing - A, Shreeji Eternity Wing - B, Shreeji Eternity Wing - C
MahaRERA — P51800054310
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors17
Sanctioned17
🅿️Closed Parking41
📅Completion2027-06-30
🏗️Proposed Floors19
Sanctioned19
🅿️Closed Parking51
📅Completion2027-06-30
🏗️Proposed Floors19
Sanctioned19
🅿️Closed Parking1
📅Completion2027-06-30

Apartment Configurations

A Wing

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 29.73 1 0 1
0%
2 BHK 44.41 1 0 1
0%
2 BHK 50.17 30 0 30
0%
2 BHK 63.64 10 0 10
0%
Shop 30.47 2 0 2
0%
Shop 52.03 1 0 1
0%
Shop 89.74 2 0 2
0%
Shop 101.26 1 0 1
0%
Shop 276.29 1 0 1
0%

B Wing

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 28.43 1 0 1
0%
2 BHK 31.22 1 0 1
0%
2 BHK 35.86 1 0 1
0%
2 BHK 43.01 1 0 1
0%
2 BHK 47.66 1 0 1
0%
2 BHK 50.17 33 0 33
0%
2 BHK 59.46 12 0 12
0%
Shop 77.29 1 0 1
0%
Shop 84.54 1 0 1
0%
Shop 101.45 1 0 1
0%
Shop 103.49 2 0 2
0%
Shop 285.77 2 0 2
0%

C Wing

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 43.48 1 0 1
0%
2 BHK 50.17 35 0 35
0%
2 BHK 54.44 4 0 4
0%
2 BHK 63.64 10 0 10
0%
Shop 33.17 1 0 1
0%
Shop 41.62 2 0 2
0%
Shop 41.71 1 0 1
0%
Shop 100.33 2 0 2
0%
Shop 374.67 1 0 1
0%

Construction Progress

A wing

Basement (if any)100%

A Wing

Excavation100%

A wing

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

A Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

A wing

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%

A Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%

A wing

Plinth100%
Podiums (if any) 66%

A Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

A wing

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

A Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.22%

A wing

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks24%

A Wing

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums11%
X number of Slabs of Super Structure0%

B Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Plinth100%
Podiums (if any) 66%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.22%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks24%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums11%
X number of Slabs of Super Structure0%

C Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Plinth100%
Podiums (if any) 66%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.22%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks24%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums11%
X number of Slabs of Super Structure0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.