Excavation100%
Podiums (if any) 100%
Basement (if any)99%
Plinth99%
Stilt Floor 48%
Slabs of Super Structure29%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks29%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises11%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%