✓ MahaRERA P51700054547RERA: no litigation reported118
Units
2028
Possession
1
Buildings
Certificate Signed
Status
Lifecycle requires verification
Ask an advisor to verify the current project and inventory status.
Source stage: New · mapped resale: 0 · mapped rental: 0 · primary status: not confirmed
01
Possession Timeline
Proposed
Dec 2028
Status
New
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
Office Space126–173 ft²On request
Shop242–329 ft²On request
1 BHK389–425 ft²On request
2 BHK514–522 ft²On request
3 BHK703 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P51700054547
Registered
2024-01-31
Litigation
No reported in source
Escrow Bank
BANK OF INDIA
Architect
Shirish G Nachane
Total FSI
6658
04
Buildings · 1 Wing(s)
Trimurti One13 floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Kalyan
19.2207089,73.1436159
19.2207089,73.1436159
▸ Explore map & Street View — for verified buyers
07
Promoter & Professionals
Hariram Dhruvnarayan ChaurasiaPartner
Kamesh Ramesh JadhavPartner
Meena Jaichand KesharwaniPartner
Ramesh sudam JadhavPartner
Vaibhav Hariram ChaurasiaPartner
09
Construction Progress
52% avgBasement (if any)100%
Excavation100%
Plinth100%
Slabs of Super Structure100%
X number of Basement(s) and Plinth100%
Stilt Floor75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
X number of Slabs of Super Structure15%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises5%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.5%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
10
Amenities
Electrical Meter Room, Sub-Station, Receiving StationFire Protection And Fire Safety RequirementsLandscaping & Tree PlantingSewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsWater Conservation, Rain water HarvestingWater Supply
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory08
Property Rates in Kalyan
Residential · Sale
₹10,000–15,000/sqft
Commercial · Sale
₹6,500–10,000/sqft
2 BHK · Rent
₹15,000–35,000/mo
Full rates
15
MahaRERA projects nearby in Kalyan
Kalas Darshan1357 unitsRgc Runwal My City Ews - Lig Building825 unitsCrown Dombivli 2778 unitsCharms Padamavati Royal Phase 2746 unitsRajgad By Bhagwati Haware – Wing - D710 unitsCrown Dombivli 1695 unitsVenus Skky City Vivanta Bldg F And Bldg G659 unitsBalaji Classica - Athena And Iris594 unitsSwaminarayan City Phase 1C592 unitsVastu Luxuria520 unitsPalava -Signet 2517 unitsCharms Padamavati Royal Phase 1460 units
?
Frequently Asked Questions
When is possession of Trimurti One?
As per MahaRERA, proposed possession is Dec 2028.
Is Trimurti One RERA-registered?
Yes — MahaRERA registration P51700054547, registered 2024-01-31. The current MahaRERA source record reports no litigations.
Who is the developer?
Trimurti Construction — 2 projects tracked on Mumbai Property Exchange. View their track record ▸
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.