UGAM SRISHTI

by UGAM BUILDERS & DEVELOPERS Partnership
Certificate SignedP52000028445
UGAM SRISHTIProject photos will appear here when available.

Project Information

RERA Certificate No.
P52000028445
Registration No.
REA52000085458
Registration Date
2021-09-08
Developer
UGAM BUILDERS & DEVELOPERS Partnership
Architect
Prabhakar
Proposed Possession
2025-06-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
1
Units Sold
1 (100%)
Buildings
5
Project Area
269.00 sq.m
Total FSI
269.00
Approved FSI
269.00
MahaRERA QR
UGAM SRISHTI
MahaRERA — P52000028445
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors6
✅Sanctioned6
🏠Habitable4
🔢Total Units1
🏡Residential1
🏗️Proposed Floors6
✅Sanctioned6
🏗️Proposed Floors6
✅Sanctioned6
🏗️Proposed Floors6
✅Sanctioned6
🏗️Proposed Floors6
✅Sanctioned6

Apartment Configurations

A WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK27.56404
0%
1BHK30.41404
0%
1BHK30.42404
0%
1BHK30.62404
0%
1BHK31.92404
0%
2BHK43.35404
0%
2BHK46.74404
0%

B WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK28.08404
0%
1BHK28.68404
0%
1BHK29.38404
0%
1BHK30.09404
0%
1RK19.4404
0%
1RK20.37404
0%

C WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK27.81404
0%
1BHK27.98404
0%
1BHK29.4404
0%
1BHK29.81404
0%
1BHK29.85404
0%
1BHK30.63404
0%
1BHK31.91404
0%
1RK20.99404
0%
1RK32.95404
0%

D WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK20.29404
0%
1BHK29.57404
0%
1BHK29.72404
0%
1BHK31.7112012
0%
1RK20.3404
0%
1RK20.68404
0%

E WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK27.56404
0%
1BHK30.42404
0%
1BHK30.69404
0%
1BHK31.71404
0%
1RK20.312012
0%

Construction Progress

A WING

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

B WING

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

C WING

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

D WING

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

E WING

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
✅Fire protection and fire safety requirements
✅Internal Roads & Footpaths
⬜Landscaping & Tree Planting
✅Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
✅Solid Waste Management And Disposal
✅Storm Water Drains
✅Street Lighting
✅Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
⬜Water conservation /Rain water harvesting