Excavation100%
Slabs of Super Structure100%
Basement (if any)95%
Plinth95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.93%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises83%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.68%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.66%
Sanitary Fittings within the flats / premises43%
Sanitary Fittings within the flats / premises42%
Podiums (if any) 0%