Nathani Heights Rehab
by Nathani Parekh Constructions Private Limited
Company
Nathani Heights RehabProject photos will appear here when available.
Project Information
RERA Certificate No.
P51900008587
Registration No.
REA51900012194
Registration Date
2021-09-09
Developer
Nathani Parekh Constructions Private Limited Company
Architect
Subodh Tari
Project Bank
AXIS BANK
Proposed Possession
2021-12-30
Revised Possession
2021-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
5301.04 sq.m
Total FSI
13558.53
Approved FSI
13558.53
Nathani Heights Rehab
MahaRERA — P51900008587
MahaRERA — P51900008587
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors36
✅Sanctioned36
Apartment Configurations
NATHANI HEIGHTS REHAB
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| R | 28.72 | 4 | 4 | 0 | 100% |
| R | 28.93 | 10 | 10 | 0 | 100% |
| R | 43.15 | 7 | 7 | 0 | 100% |
| R | 44.95 | 33 | 33 | 0 | 100% |
| R | 45.14 | 4 | 4 | 0 | 100% |
| R | 47.46 | 17 | 17 | 0 | 100% |
| R | 58.76 | 10 | 10 | 0 | 100% |
| R | 59.79 | 1 | 1 | 0 | 100% |
| R | 60.2 | 7 | 7 | 0 | 100% |
| R | 60.5 | 3 | 3 | 0 | 100% |
| R | 62.22 | 10 | 10 | 0 | 100% |
| R | 62.84 | 3 | 3 | 0 | 100% |
| R | 63.91 | 1 | 1 | 0 | 100% |
| R | 64.41 | 6 | 6 | 0 | 100% |
| R | 65.15 | 11 | 11 | 0 | 100% |
| R | 65.28 | 6 | 6 | 0 | 100% |
| R | 65.76 | 10 | 10 | 0 | 100% |
| R | 67.72 | 3 | 3 | 0 | 100% |
| R | 68.19 | 1 | 1 | 0 | 100% |
| R | 69.99 | 14 | 14 | 0 | 100% |
| R | 70.24 | 16 | 16 | 0 | 100% |
| R | 71.23 | 20 | 20 | 0 | 100% |
| R | 79.93 | 5 | 5 | 0 | 100% |
| R | 80.17 | 11 | 11 | 0 | 100% |
| R | 85.53 | 7 | 7 | 0 | 100% |
| R | 96.62 | 2 | 2 | 0 | 100% |
| R | 99.52 | 2 | 2 | 0 | 100% |
Construction Progress
NATHANI HEIGHTS REHAB
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
⬜Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
⬜Fire protection and fire safety requirements
⬜Internal Roads & Footpaths
⬜Landscaping & Tree Planting
⬜Open Parking
⬜Sewerage (Chamber, Lines, Septic Tank , STP)
⬜Solid Waste Management And Disposal
⬜Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
⬜Water Supply
⬜Water conservation /Rain water harvesting