Pandurangpark by Chaitanya Builders & Developers

Chaitanya Builders & Developers
πŸ“ Boisar, Palghar Β· 401501
225
Units
2025
Possession
16
Buildings
Kept in Abeyance
Status
01

Possession Timeline

Proposed
Jun 2025
Revised
Jun 2026
Status
On-Going Project
⚠ Possession revised later than originally proposed β€” per MahaRERA.
02

Unit Configurations (per MahaRERA)

ConfigurationCarpetIndicative Price
1 BHK265–387 ftΒ²On request
2 BHK284–574 ftΒ²On request
Configurations & carpet per MahaRERA filing Β· indicative price = locality rate Γ— carpet (not the developer's quote).
πŸ’¬ Live availability, floor plans & today's price β€” on WhatsApp
03

RERA Trust Record

MahaRERA No.
P99000020314
Registered
β€”
Litigation
None on record
Escrow Bank
HDFC BANK
Architect
β€”
Total FSI
10768
04

Buildings Β· 16 Wing(s)

Build No 3 B Wing Proposedβ€” floors Β· β€” units
Building No 1 A Wingβ€” floors Β· β€” units
Building No 1 A Wing Proposedβ€” floors Β· β€” units
Building No 1 B Wingβ€” floors Β· β€” units
Building No 1 B Wing Proposedβ€” floors Β· β€” units
Building No 1 C Wingβ€” floors Β· β€” units
Building No 1 C Wing Proposedβ€” floors Β· β€” units
Building No 2 A Wingβ€” floors Β· β€” units
05

Land DNA Β· Genesis

Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06

Location

πŸ“ Boisar
β–Έ Explore map & Street View β€” for verified buyers
09

Construction Progress

0% avg
Excavation0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%
10

Amenities

Aggregate area of recreational Open SpaceLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And DisposalStorm Water DrainsStreet LightingTreatment And Disposal Of Sewage And Sullage WaterWater Conservation, Rain water HarvestingWater Supply
12

Floor Plans, E-Brochure & Payment Plans

πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13

EMI Calculator

β€”
08

Property Rates in Boisar

Residential Β· Sale
β‚Ή4,500–6,000/sqft
Commercial Β· Sale
β‚Ή2,000–6,000/sqft
2 BHK Β· Rent
β‚Ή10,000–30,000/mo
14

More by Chaitanya Builders & Developers

Ethics Oliver Mahim Β· Under ConstructionGanapati Baug CHSLBorivali West Β· Under ConstructionChaitanya Om ShivamBorivali West Β· Sold OutChaitanya ShreyasAndheri West Β· Sold OutChaitanya NishigandhDadar West Β· Sold OutChaitanya AnandAndheri West Β· Sold Out
15

MahaRERA projects nearby in Boisar

Roop Rajat Park Phase 3420 unitsRajmandir Gardens243 unitsAgami Infinity Park 3152 unitsBALAJI COMPLEX PHASE-276 unitsParivar D Wing70 unitsTHAKUR DHAM BUILDING NO 1 TYPE B 166 unitsAVASAR RESIDENCY62 unitsDARSHAN COMPLEX42 unitsSAI SANSKRUTI36 unitsMAHAVIR EMERALD WING C28 unitsMAHAVIR EMERALD28 unitsMAHAVIR EMERALD WING B28 units
?

Frequently Asked Questions

When is possession of PANDURANGPARK?

As per MahaRERA, proposed possession is Jun 2025, revised to Jun 2026.

Is PANDURANGPARK RERA-registered?

Yes β€” MahaRERA registration P99000020314. No litigations on record.

Who is the developer?

Chaitanya Builders & Developers β€” 20 projects tracked on Mumbai Property Exchange.

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Boisar β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
Our advisor replies on WhatsApp within 2 working hours (9am–8pm IST).
βœ“ MahaRERA P51900079270β˜… Featured
Runwal Enterprises
7 Mahalaxmi, Mahalaxmi
2 BHK, 3 BHK, 4 BHK Β· β‚Ή56,000/sq.ft Β· Possession Dec 2031
Learn more β€Ί

πŸ“° Latest Mumbai Property News

View all news β†’