List PropertyWhatsApp
New ProjectsBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your PropertyπŸ’¬ WhatsApp Us
🏠 Mumbai property advisory & dataOperating since 1995βœ“ MahaRERA A51800043517βœ“ RERA-verified project data🟒 We reply in minutes on WhatsApp
P
βœ“ MahaRERA PM1180002500115βœ“ Clear

Pearl by Prithvi Property Developers

Prithvi Property Developers
πŸ“ Tata Colony, Mumbai Suburban Β· 400081
β€”
Units
2029
Possession
1
Buildings
Certificate Signed
Status
01

Possession Timeline

Proposed
Dec 2029
Status
New
02

Unit Configurations (per MahaRERA)

03

RERA Trust Record

MahaRERA No.
PM1180002500115
Registered
2025-06-23
Litigation
None on record
Escrow Bank
IDFC First Bank Ltd
Architect
β€”
Total FSI
5600
04

Buildings Β· 1 Wing(s)

PEARL, BUILDING NO 131 floors Β· β€” units
05

Land DNA Β· Genesis

Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06

Location

πŸ“ Tata Colony
19.075614692030477,72.87495341796877
β–Έ Explore map & Street View β€” for verified buyers
07

Promoter & Professionals

BABADIN GAYASHANKER TRIPATHIPARTNER
DINESH KALURAM YADAVPARTNER
MADHAV RAMESH KODEPARTNER
UMESH RAJARAM SHINDEPARTNER
09

Construction Progress

0% avg
Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 0%
12

Floor Plans, E-Brochure & Payment Plans

πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13

EMI Calculator

β€”
14

More by Prithvi Property Developers

Nebula EmpressKhar West Β· Under ConstructionAtlantis TowerKhar West Β· Under Construction
15

MahaRERA projects nearby in Tata Colony

Mulund Ravi KailashSHIV DARSHAN APARTMENTSai Darshan ApartmentMulund Ravi Kailash 16Th, 17Th, 18Th Floor
?

Frequently Asked Questions

When is possession of Pearl?

As per MahaRERA, proposed possession is Dec 2029.

Is Pearl RERA-registered?

Yes β€” MahaRERA registration PM1180002500115, registered 2025-06-23. No litigations on record.

Who is the developer?

Prithvi Property Developers β€” 3 projects tracked on Mumbai Property Exchange.

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Tata Colony β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
Our advisor replies on WhatsApp within 2 working hours (9am–8pm IST).
βœ“ MahaRERA P51900006299β˜… Featured
Godrej Properties
Godrej Avenue Eleven B, Mahalaxmi
4 BHK Β· β‚Ή69,000/sq.ft Β· Possession Jan 2029
Learn more β€Ί

πŸ“° Latest Mumbai Property News

View all news β†’