Shivsagar ChslProject photos will appear here when available.
Project Information
RERA Certificate No.
P51800077688
Registration No.
REA51800164992
Registration Date
2025-07-08
Developer
Girija Developers Partnership
Architect
Vinayak Sahasrabudhe
Project Bank
HDFC BANK
Proposed Possession
2029-04-30
Total Units
26
Units Sold
7 (27%)
Buildings
1
Project Area
525.00 sq.m
Total FSI
1417.50
Approved FSI
1414.68
Shivsagar Chsl
MahaRERA — P51800077688
MahaRERA — P51800077688
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors10
✅Sanctioned10
🔢Total
Units26
🏡Residential26
Apartment Configurations
SHIVSAGAR CHSL
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1BHK | 38.85 | 3 | 1 | 2 | 33% |
| 2BHK | 51.49 | 3 | 2 | 1 | 67% |
| 2BHK | 55.5 | 1 | 0 | 1 | 0% |
| LANDOWNER 1BHK | 38.85 | 4 | 4 | 0 | 100% |
| LANDOWNER 2BHK | 51.49 | 4 | 4 | 0 | 100% |
| LANDOWNER 2BHK | 55.5 | 6 | 6 | 0 | 100% |
Construction Progress
SHIVSAGAR CHSL
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station60%
⬜Energy managemcnt
✅Fire protection and fire safety requirements
⬜Internal Roads & Footpaths
⬜Landscaping & Tree Planting
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
✅Solid Waste Management And Disposal80%
✅Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply100%
✅Water conservation /Rain water harvesting