List PropertyWhatsApp
Best DealsNew Projects๐Ÿ—บ๏ธ Projects MapBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your Property๐Ÿ’ฌ WhatsApp Us
Mumbai property advisory & dataOperating since 1995โœ“ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

SUPER HOMEZ-HARMONY PHASE II

by MANGALMURTI VINAY UNIQUE REALTORS
Certificate SignedPR1241012502347
SUPER HOMEZ-HARMONY PHASE IIProject photos will appear here when available.

Project Information

RERA Certificate No.
PR1241012502347
Developer
MANGALMURTI VINAY UNIQUE REALTORS
Proposed Possession
2028-10-30
Total Units
337
Units Sold
49 (15%)
Buildings
4
MahaRERA QR
SUPER HOMEZ-HARMONY PHASE II
MahaRERA โ€” PR1241012502347
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors8
โœ…Sanctioned8
๐Ÿ Habitable8
๐Ÿ”ขTotal Units84
๐ŸกResidential74
๐ŸขNon-Residential10
๐Ÿ—๏ธProposed Floors8
โœ…Sanctioned8
๐Ÿ Habitable8
๐Ÿ”ขTotal Units92
๐ŸกResidential81
๐ŸขNon-Residential11
๐Ÿ—๏ธProposed Floors8
โœ…Sanctioned8
๐Ÿ Habitable8
๐Ÿ”ขTotal Units87
๐ŸกResidential87
๐Ÿ—๏ธProposed Floors8
โœ…Sanctioned8
๐Ÿ Habitable8
๐Ÿ”ขTotal Units74
๐ŸกResidential74

Construction Progress

Building Number 5

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks55%
Stilt Floor60%

Building Number 6

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks55%
Stilt Floor60%

Building Number 7

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
Stilt Floor60%

Building Number 8

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
Stilt Floor60%

RERA Registered Amenities

โœ…Aggregate area of recreational Open Space
โฌœCommunity Buildings
โœ…Electrical meter room, sub-station, receiving station
โœ…Energy managemcnt
โœ…Fire protection and fire safety requirements
โœ…Internal Roads & Footpaths50%
โœ…Landscaping & Tree Planting
โœ…Open Parking
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)
โœ…Solid Waste Management And Disposal
โœ…Storm Water Drains
โœ…Street Lighting
โœ…Treatment And Disposal Of Sewage And Sullage Water
โœ…Water Supply
โœ…Water conservation /Rain water harvesting

Latest Mumbai Property News

View all news โ†’
CallWhatsApp
๐Ÿ‘‹ Looking for the right project? Let me help you find it!
๐Ÿ—๏ธ
MPE Project Advisor
โ— Online now