Yogi Niwas

by Elite Infrastructure Partnership
Certificate SignedP51700002560
Yogi NiwasProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700002560
Registration No.
REA51700005897
Registration Date
2017-08-01
Developer
Elite Infrastructure Partnership
Architect
Jitendra S Patel Samarthya Engineers
Project Bank
IDBI BANK
Proposed Possession
2018-06-30
Revised Possession
2018-06-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
12985.51 sq.m
Total FSI
18493.37
Approved FSI
10696.91
MahaRERA QR
Yogi Niwas
MahaRERA โ€” P51700002560
Scan to verify on MahaRERA portal

Wing-wise Details

๐Ÿ—๏ธProposed Floors13
โœ…Sanctioned13

Apartment Configurations

BUILDING NO 9

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK28.27110
100%
1BHK30.0212120
100%
1BHK30.18220
100%
1BHK31.0212120
100%
1BHK31.8523221
96%
2BHK36.6448444
92%
2BHK37.61440
100%

Construction Progress

BUILDING NO 9

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.25%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
Stilt Floor0%

RERA Registered Amenities

โœ…Aggregate area of recreational Open Space30%
โœ…Community Buildings100%
โœ…Electrical meter room, sub-station, receiving station50%
โœ…Energy managemcnt50%
โœ…Fire protection and fire safety requirements
โฌœInternal Roads & Footpaths
โœ…Landscaping & Tree Planting
โœ…Open Parking50%
โœ…Sewerage (Chamber, Lines, Septic Tank , STP)50%
โฌœSolid Waste Management And Disposal
โœ…Storm Water Drains50%
โœ…Street Lighting
โฌœTreatment And Disposal Of Sewage And Sullage Water
โœ…Water Supply
โœ…Water conservation /Rain water harvesting50%