A first look at DGS Sheetal Shree Ramkunj
DGS Sheetal Shree Ramkunj is a residential project on Haji Bapu Road, near Post Office, Malad East, Mumbai 400097. It is registered with MahaRERA under P51800078253 (registered 2024-11-29). DGS Sheetal Shree Ramkunj is sold out by the developer; ask MPE for resale or rental flats in this building. The project has 81 units across 1 building of up to 9 floors. It offers 1, 2 & 3 BHK homes with carpet areas of 383–1,000 sq ft. MahaRERA proposed possession: Apr 2030.
Ask an advisor to check current resale or rental availability.
Unit configurations filed with MahaRERA (6)
DGS Sheetal Shree Ramkunj floor plans
2Floor plans are indicative, as shared by the developer, and subject to change.
About DGS Sheetal Shree Ramkunj
Location
DGS Sheetal Shree Ramkunj stands on Haji Bapu Road, near Post Office in Malad East, Mumbai 400097, in the Mumbai Suburban district. Across 233 recent resale listings on MPE, homes in Malad East have a median asking rate of ₹30,300 per sq ft, and a 2 BHK typically rents for about ₹65,000 a month.
MahaRERA record
DGS Sheetal Shree Ramkunj is registered with MahaRERA under P51800078253, dated 29 November 2024. The registered promoter is D.G.S. Land Developers (India) Pvt. Ltd.. The filing lists 1 wing: SHEETAL SHREE RAM KUNJ with 81 units over 9 floors. According to MahaRERA, the architect on record is UDANI CONSULTANTS PVT LTD and the project escrow account is with Bharat Cooperative Bank Mumbai Ltd.
Homes and prices
Homes on offer are 1 BHK of 383 sq ft at ₹76.64 Lac; 2 BHK of 541 sq ft at ₹1.08 Cr; 3 BHK of 1,000 sq ft at ₹2 Cr (carpet area), as on 09 Jul 2026. That works out to about ₹20,000 per sq ft of carpet, 34% below the locality's resale median. Prices are indicative and should be reconfirmed with the developer before booking.
Construction and possession
The latest MahaRERA progress report shows foundation at 60%, structure at 35%, finishing at 0%, services at 8%. Proposed possession is Apr 2030.
Developer track record
DGS Group has 44 projects tracked on Mumbai Property Exchange, 28 of them delivered (ready or sold out).
Buyer demand in Malad East
In the last 90 days, buyers and tenants registered 22 requirements for Malad East with Mumbai Property Exchange, 6 of them to buy and 8 specifically for 1, 2 & 3 BHK homes.
Developer's description ▾
Malad East market
prices, rents & ratesPrice vs locality
Malad East — resale, rent & yield
This project is quoted around ₹19,991/sqft — 34% below resale here.
From MPE live listings, last 18 months · Mumbai price index ›
Property rates in Malad East
Upcoming projects & infrastructure in Malad East
take an informed decision47 MahaRERA projects are due to hand over in Malad East between 2026 and 2030; the nearest upcoming infrastructure to DGS Sheetal Shree Ramkunj is the Goregaon-Mulund Link Road (GMLR), 2.1 km away (under construction · due 2028).
- 🚇Goregaon-Mulund Link Road (GMLR)Under construction · due 20282.1 km
Ask on WhatsApp — we answer right in the chat with live asking prices, listings and registered sales for Malad East, then an advisor calls about your budget and configuration.
Prices and timelines are indicative and subject to change. See the disclaimer at the foot of this page.
RERA record & possession
Buildings · 1 wing
81 unitsLocation
Construction progress
per MahaRERASee all 11 stages ▾
What you pay, and when
an exampleThis is just an example of the cash flows for buying a home, not a quote or a payment demand. Your agreement and the developer's schedule decide the actual amounts.
In an under-construction project, you don't pay everything on day one. Under the MahaRERA model agreement, the developer can only ask for money as each stage is finished: about 10% at booking, 30% at agreement, then more as the plinth, slabs, walls, fittings and lifts are done, and the last 5% at possession. The more a building is finished, the more you pay up front.
Example: 2 BHK · 541 sq ft at ₹1.08 Cr (the price recorded above).
- ○ Plinth complete45% paid by then
- ○ Slabs complete70% paid by then
- ○ Walls, plaster & flooring75% paid by then
- ○ Sanitary fittings80% paid by then
- ○ Staircases, lift wells & lobbies85% paid by then
- ○ Lifts, pumps, plumbing & elevation95% paid by then
- ○ Possession100%
With a home loan: banks usually fund up to 75% (₹81.0 L here), released stage by stage, so your own money is about ₹27.0 L plus stamp duty and GST. Until possession you pay interest only on what the bank has released; after that the full EMI is roughly ₹70,300/month (8.5%, 20 years).
Indicative only. Rates, GST (1% on affordable homes), loan eligibility and the stage schedule vary. Plan your cash flow with an advisor before you book.
💬 Talk through the numbers with an MPE advisorAmenities
11+3 more ▾
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Ask about resale or rental optionsResale Flats for Sale in Malad East
4Flats for Rent in Malad East
4Commercial for Sale in Malad East
1Commercial Projects in Malad East
MahaRERA projects nearby in Malad East
Frequently Asked Questions
Where is DGS Sheetal Shree Ramkunj located?
DGS Sheetal Shree Ramkunj is on Haji Bapu Road, near Post Office, Malad East, Mumbai 400097.
What is the price of DGS Sheetal Shree Ramkunj?
DGS Sheetal Shree Ramkunj is sold out by the developer; ask MPE for resale or rental flats in this building.
What configurations and carpet areas does DGS Sheetal Shree Ramkunj offer?
1 BHK – 383 sq ft carpet; 2 BHK – 541 sq ft carpet; 3 BHK – 1,000 sq ft carpet.
When is possession of DGS Sheetal Shree Ramkunj?
As per MahaRERA, proposed possession is Apr 2030.
Is DGS Sheetal Shree Ramkunj RERA-registered?
Yes — MahaRERA registration P51800078253, registered 2024-11-29.
How many units does DGS Sheetal Shree Ramkunj have?
MahaRERA records 81 units across 8 buildings, up to 9 floors.
Who is the developer of DGS Sheetal Shree Ramkunj?
DGS Group (D.G.S. Land Developers (India) Pvt. Ltd.) — 44 projects tracked on Mumbai Property Exchange. View their track record ▸
How many new projects are coming up in Malad East?
47 MahaRERA-registered projects in Malad East are due for possession between 2026 and 2030, as per MahaRERA registrations. Timelines can change.
What metro and infrastructure is near DGS Sheetal Shree Ramkunj?
Goregaon-Mulund Link Road (GMLR) — under construction · due 2028, 2.1 km away. Timelines are as announced and can change.