List your propertyWhatsApp
Best dealsNew projectsInvestProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNewsLog in+ List your property — sell or leaseWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp
Primary inventory recordedMahaRERA P51700047989

Gandhare · Mumbai

Mangeshi Valley

Gandhare · by Mangeshi Group (Mangesh Dashrath Gaikar)

Updated Sep 2026

223
Units
2026
Possession
1
Buildings
Certificate Signed
Status

A first look at Mangeshi Valley

Mangeshi Valley is a residential project in Gandhare, Mumbai 421301. It is registered with MahaRERA under P51700047989. The project has 223 units across 1 building of up to 22 floors. It offers 1 BHK homes with carpet areas of 482 sq ft, priced ₹55 Lac as on 30 Jul 2026 (indicative). The quoted rate is about ₹11,400 per sq ft. MahaRERA proposed possession: Jul 2026.

Primary inventory recorded.

Ask an advisor to verify current developer inventory and price.

Availability & Pricing

TypeCarpetPriceAvail
1 BHK482 ft²₹55 Lac—

Prices as on 30 Jul 2026. Approximate pricing as on that date. Prices are indicative, subject to change and to reconfirmation with the developer.

💬 Request latest price on WhatsApp
Unit configurations filed with MahaRERA (3)
ConfigurationCarpetIndicative Price
Shop104–228 ft²₹12 L–₹26 L
1 BHK392–538 ft²₹45 L–₹61 L
2 BHK510–560 ft²₹58 L–₹64 L
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor

About Mangeshi Valley

Location

The project is in Gandhare, Mumbai 421301, in the Thane district.

MahaRERA record

Mangeshi Valley is registered with MahaRERA under P51700047989. The registered promoter is Mangesh Dashrath Gaikar. The filing lists 1 wing: 1 with 223 units over 22 floors. According to MahaRERA, the project escrow account is with Thane Bharat Sahakari Bank Ltd.

Homes and prices

Configurations recorded are 1 BHK of 482 sq ft at ₹55 Lac (carpet area), as on 30 Jul 2026. That works out to about ₹11,400 per sq ft of carpet. Prices are indicative and should be reconfirmed with the developer before booking.

Construction and possession

MahaRERA progress reports show construction has not started yet on any of the 11 tracked stages. Proposed possession is Jul 2026.

Developer track record

Mangeshi Group has 4 projects tracked on Mumbai Property Exchange, 1 of them delivered (ready or sold out). Other projects by the same developer include Velvet lifestyle, Mangeshi Tulip, Mangeshi 23 Carat Gold.

Gandhare market

prices, rents & rates

Price vs locality

₹11,411
/sqft · Gandhare rate-band mid-point ₹30,000
62% below mid-point

Property rates in Gandhare

Residential · Sale
₹15,000–45,000/sqft
Commercial · Sale
₹15,000–45,000/sqft
2 BHK · Rent
₹45,000–100,000/mo

Upcoming projects & infrastructure in Kalyan

take an informed decision

163 MahaRERA projects are due to hand over in Kalyan between 2026 and 2030; the nearest upcoming infrastructure to Mangeshi Valley is the Line 5 Orange, 1.9 km away (under construction · due 2027).

163
MahaRERA projects handing over in the next 5 years
in Kalyan
New projects in Kalyan by possession year
6
2026
33
2027
47
2028
37
2029
40
2030
Metro & infrastructure near Mangeshi Valley
  • 🛣️Mumbai-Nagpur Samruddhi MahamargOpened 20261.3 km
  • 🚇Line 5 OrangeUnder construction · due 20271.9 km
  • 🚇Line 12 OrangeUnder construction · due 20261.9 km
  • 🛣️Mumbai-Delhi Expressway (Vadodara link)Under construction · due 20282.0 km
In the full Kalyan report

🔒 Units handing over each year · price by BHK · years to absorb supply · competing projects · infra impact on prices

Prices and timelines are indicative and subject to change. See the disclaimer at the foot of this page.

RERA record & possession

Possession (proposed)
Jul 2026
Project status
New
MahaRERA No.
P51700047989
Data last updated
Sep 2026
Registered
—
Escrow Bank
Thane Bharat Sahakari Bank Ltd
Architect
—
Total FSI
7,924

Buildings · 1 wing

223 units
1 · 22 fl · 223 u

Location

Map data © OpenStreetMap contributors · location indicativeOpen larger map ›

Construction progress

per MahaRERA
🏗️ Not started yet — all 11 MahaRERA construction stages are at 0%.
See all 11 stages ▾
Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terr…0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipm…0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within…0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and …0%
Stilt Floor0%

What you pay, and when

an example

This is just an example of the cash flows for buying a home, not a quote or a payment demand. Your agreement and the developer's schedule decide the actual amounts.

In an under-construction project, you don't pay everything on day one. Under the MahaRERA model agreement, the developer can only ask for money as each stage is finished: about 10% at booking, 30% at agreement, then more as the plinth, slabs, walls, fittings and lifts are done, and the last 5% at possession. The more a building is finished, the more you pay up front.

Example: 1 BHK · 482 sq ft at ₹55.0 L (the price recorded above).

Due soon after booking~₹16.5 L30%, stages already done
Balance till possession~₹38.5 Las the last stages finish
Stamp duty + GST~₹3.3 L + ₹2.8 L6% + 5%, plus ~₹30,000 registration
  1. ○ Plinth complete45% paid by then
  2. ○ Slabs complete70% paid by then
  3. ○ Walls, plaster & flooring75% paid by then
  4. ○ Sanitary fittings80% paid by then
  5. ○ Staircases, lift wells & lobbies85% paid by then
  6. ○ Lifts, pumps, plumbing & elevation95% paid by then
  7. ○ Possession100%

With a home loan: banks usually fund up to 75% (₹41.2 L here), released stage by stage, so your own money is about ₹13.8 L plus stamp duty and GST. Until possession you pay interest only on what the bank has released; after that the full EMI is roughly ₹35,800/month (8.5%, 20 years).

Indicative only. Rates, GST (1% on affordable homes), loan eligibility and the stage schedule vary. Plan your cash flow with an advisor before you book.

💬 Talk through the numbers with an MPE advisor

Amenities

12
Electrical meter room, sub-station, r…Energy managemcntFire protection and fire safety requi…Internal Roads & FootpathsLandscaping & Tree PlantingSewerage (Chamber, Lines, Septic Tank…Solid Waste Management And DisposalStorm Water Drains
+4 more ▾
Street LightingTreatment And Disposal Of Sewage And …Water SupplyWater conservation /Rain water harvesting

Next steps — clarity before you step out

Buying a home is not a quick decision. In association with developers, Mumbai Property Exchange sets up the video briefings (Google Meet, Teams or WhatsApp video), the site visits and the paperwork questions — so your homework is done before you commit an afternoon.

Resale Flats for Sale in Gandhare

3

Flats for Rent in Gandhare

4

Commercial for Sale in Gandhare

1

Commercial for Lease in Gandhare

2

Commercial Projects in Gandhare

More by Mangeshi Group (Mangesh Dashrath Gaikar)

Compare Mangeshi Ambar with similarly priced projects nearby

MahaRERA projects nearby in Gandhare

Frequently Asked Questions

Where is Mangeshi Valley located?

Mangeshi Valley is in Gandhare, Mumbai 421301.

What is the price of Mangeshi Valley?

1 BHK homes are priced ₹55 Lac as on 30 Jul 2026, about ₹11,400 per sq ft. Prices are indicative and subject to reconfirmation with the developer.

What configurations and carpet areas does Mangeshi Valley offer?

1 BHK – 482 sq ft carpet at ₹55 Lac.

When is possession of Mangeshi Valley?

As per MahaRERA, proposed possession is Jul 2026.

Is Mangeshi Valley RERA-registered?

Yes — MahaRERA registration P51700047989.

How many units does Mangeshi Valley have?

MahaRERA records 223 units across 1 building, up to 22 floors.

Who is the developer of Mangeshi Valley?

Mangeshi Group (Mangesh Dashrath Gaikar) — 4 projects tracked on Mumbai Property Exchange. View their track record ▸

How many new projects are coming up in Kalyan?

163 MahaRERA-registered projects in Kalyan are due for possession between 2026 and 2030, as per MahaRERA registrations. Timelines can change.

What metro and infrastructure is near Mangeshi Valley?

Mumbai-Nagpur Samruddhi Mahamarg — opened 2026, 1.3 km away; Line 5 Orange — under construction · due 2027, 1.9 km away; Line 12 Orange — under construction · due 2026, 1.9 km away; Mumbai-Delhi Expressway (Vadodara link) — under construction · due 2028, 2.0 km away. Timelines are as announced and can change.

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.

Disclaimer. Information on this page is compiled from MahaRERA registrations, public infrastructure announcements, developer materials and Mumbai Property Exchange listings. Prices, availability, possession dates and infrastructure timelines are indicative, subject to change, and updated periodically (last updated 2026-09-28). This is not an offer or an advertisement by the developer; please verify all details with the developer and on MahaRERA before deciding. Mumbai Property Exchange, MahaRERA agent A51800043517.
Are you the developer and see something wrong? Report a correction on WhatsApp — we verify and update.
SOURCE · MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA · RERA A51800043517 · EST. 1995
💬WhatsApp📅Book site visit📞Call back

Latest Mumbai Property News

View all news →