Worli Sea Face · Mumbai
The Imperial Worli
Khan Abdul Gaffar Khan Road, Worli Sea Face · by D&A Realty
Updated Oct 2026
Worli Sea FacePhotos from the project record · tap to enlarge

A first look at The Imperial Worli
The Imperial Worli is a residential project by D&A Realty on Khan Abdul Gaffar Khan Road, Worli Sea Face, Mumbai 400018. It is registered with MahaRERA under P51900076737 (registered 2024-06-27). The project has 15 units across 1 building of up to 31 floors. It offers 4 BHK homes with carpet areas of 6,682 sq ft, priced ₹106 Cr as on 09 Jul 2026 (indicative). The quoted rate is about ₹160,000 per sq ft. MahaRERA proposed possession: Oct 2028.
Ask an advisor to verify current developer inventory and price.
Availability & Pricing
Prices as on 09 Jul 2026. Approximate pricing as on that date. Prices are indicative, subject to change and to reconfirmation with the developer.
💬 Request latest price on WhatsAppUnit configurations filed with MahaRERA (1)
About The Imperial Worli
Location
The Imperial Worli stands on Khan Abdul Gaffar Khan Road in Worli Sea Face, Mumbai 400018, in the Mumbai City district.
MahaRERA record
The MahaRERA registration number is P51900076737, issued on 27 June 2024. The registered promoter is D & A Infra Heritage Private Limited. The filing lists 1 wing: The Imperial Worli over 31 floors. Per the registration, the project escrow account is with HDFC Bank.
Homes and prices
Homes on offer are Duplex of 6,682 sq ft at ₹106 Cr (carpet area), as on 09 Jul 2026. That works out to about ₹158,600 per sq ft of carpet. Prices are indicative and should be reconfirmed with the developer before booking.
Construction and possession
The latest MahaRERA progress report shows foundation at 20%, structure at 0%, finishing at 0%, services at 0%. Proposed possession is Oct 2028.
Developer track record
D&A Realty has 3 projects tracked on Mumbai Property Exchange, 1 of them delivered (ready or sold out). Other projects by the same developer include Lotus Celestia, Lotus Ananya, Lotus Sky Plaza.
Developer's description ▾
Upcoming projects & infrastructure in Tardeo
take an informed decision7 MahaRERA projects are due to hand over in Tardeo between 2027 and 2031; the nearest upcoming infrastructure to The Imperial Worli is the Line 11 Green, 2.6 km away (approved).
Supply is not evenly spread — one year carries about a third of it.
- 🛣️Coastal Road (Phase 1)Opened 20240.1 km
- 🚇Line 3 AquaOpened 20251.2 km
- 🚇Line 11 GreenApproved2.6 km
Ask on WhatsApp — we answer right in the chat with live asking prices, listings and registered sales for Tardeo, then an advisor calls about your budget and configuration.
Prices and timelines are indicative and subject to change. See the disclaimer at the foot of this page.
RERA record & possession
Buildings · 1 wing
Location
Construction progress
per MahaRERASee all 11 stages ▾
What you pay, and when
an exampleThis is just an example of the cash flows for buying a home, not a quote or a payment demand. Your agreement and the developer's schedule decide the actual amounts.
In an under-construction project, you don't pay everything on day one. Under the MahaRERA model agreement, the developer can only ask for money as each stage is finished: about 10% at booking, 30% at agreement, then more as the plinth, slabs, walls, fittings and lifts are done, and the last 5% at possession. The more a building is finished, the more you pay up front.
Example: Duplex · 6682 sq ft at ₹106.00 Cr (the price recorded above).
- ○ Plinth complete45% paid by then
- ○ Slabs complete70% paid by then
- ○ Walls, plaster & flooring75% paid by then
- ○ Sanitary fittings80% paid by then
- ○ Staircases, lift wells & lobbies85% paid by then
- ○ Lifts, pumps, plumbing & elevation95% paid by then
- ○ Possession100%
With a home loan: banks usually fund up to 75% (₹79.50 Cr here), released stage by stage, so your own money is about ₹26.50 Cr plus stamp duty and GST. Until possession you pay interest only on what the bank has released; after that the full EMI is roughly ₹68.99 L/month (8.5%, 20 years).
Indicative only. Rates, GST (1% on affordable homes), loan eligibility and the stage schedule vary. Plan your cash flow with an advisor before you book.
💬 Talk through the numbers with an MPE advisorAmenities
11+3 more ▾
Next steps — clarity before you step out
Buying a home is not a quick decision. In association with developers, Mumbai Property Exchange sets up the video briefings (Google Meet, Teams or WhatsApp video), the site visits and the paperwork questions — so your homework is done before you commit an afternoon.
More by D&A Realty
MahaRERA projects nearby in Worli Sea Face
Frequently Asked Questions
Where is The Imperial Worli located?
The Imperial Worli is on Khan Abdul Gaffar Khan Road, Worli Sea Face, Mumbai 400018.
What is the price of The Imperial Worli?
4 BHK homes are priced ₹106 Cr as on 09 Jul 2026, about ₹160,000 per sq ft. Prices are indicative and subject to reconfirmation with the developer.
What configurations and carpet areas does The Imperial Worli offer?
Duplex – 6,682 sq ft carpet at ₹106 Cr.
When is possession of The Imperial Worli?
As per MahaRERA, proposed possession is Oct 2028.
Is The Imperial Worli RERA-registered?
Yes — MahaRERA registration P51900076737, registered 2024-06-27.
How many units does The Imperial Worli have?
MahaRERA records 15 units across 1 building, up to 31 floors.
Who is the developer of The Imperial Worli?
D&A Realty — 3 projects tracked on Mumbai Property Exchange. View their track record ▸
How many new projects are coming up in Tardeo?
7 MahaRERA-registered projects in Tardeo are due for possession between 2027 and 2031, as per MahaRERA registrations. Timelines can change.
What metro and infrastructure is near The Imperial Worli?
Coastal Road (Phase 1) — opened 2024, 0.1 km away; Line 3 Aqua — opened 2025, 1.2 km away; Line 11 Green — approved, 2.6 km away. Timelines are as announced and can change.
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.