Garden Avenue - K K3 by Sridutt Constructions

πŸ“ Virar West, Palghar Β· 401303
427
Units
2023
Possession
5
Buildings
Certificate Signed
Status
01

Possession Timeline

Proposed
Dec 2023
Revised
Dec 2023
Status
Ongoing
02

Unit Configurations (per MahaRERA)

ConfigurationCarpetIndicative Price
1 BHK345–377 ftΒ²On request
2 BHK470–565 ftΒ²On request
Shop110–1,418 ftΒ²On request
Configurations & carpet per MahaRERA filing Β· indicative price = locality rate Γ— carpet (not the developer's quote).
πŸ’¬ Live availability, floor plans & today's price β€” on WhatsApp
03

RERA Trust Record

MahaRERA No.
P99000007110
Registered
2021-09-09
Litigation
None on record
Escrow Bank
KOTAK MAHINDRA BANK LIMITED
Architect
Divyesh Shah
Total FSI
18797
04

Buildings Β· 5 Wing(s)

K1016 floors Β· β€” units
K716 floors Β· β€” units
K7a16 floors Β· β€” units
K816 floors Β· β€” units
K916 floors Β· β€” units
05

Land DNA Β· Genesis

Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06

Location

πŸ“ Virar West
19.471381999999998,72.804897999999994
β–Έ Explore map & Street View β€” for verified buyers
07

Promoter & Professionals

Jyotsana Purushottam PatelPartner
09

Construction Progress

100% avg
Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
10

Amenities

Aggregate area of recreational Open SpaceElectrical Meter Room, Sub-Station, Receiving StationEnergy managementFire Protection And Fire Safety RequirementsLandscaping & Tree PlantingOPEN PARKINGSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And DisposalStorm Water DrainsStreet LightingTreatment And Disposal Of Sewage And Sullage WaterWater Conservation, Rain water HarvestingWater Supply
12

Floor Plans, E-Brochure & Payment Plans

πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13

EMI Calculator

β€”
15

MahaRERA projects nearby in Virar West

MAYFAIR VIRAR GARDENS BUILDING NO 17, 18, 19, 23A, 26, 27901 unitsYASHWANT AVENUE 2209 unitsVIVA CITY - A3140 unitsVIVA CITY - A4138 unitsYASHWANT PRESTIGE112 unitsSHANTI NIWAS108 unitsMAHAVIR ASHISH CO-OPERATIVE HOUSING SOCIETY LTD78 unitsYASHWANT CIRCLE70 unitsAvanti Heights70 unitsSHREE GAYATRI CHSL56 unitsHIRUBAI RESIDENCY39 unitsSHREE SHIVKRUPA CO OPERATIVE HOUSING SOCIETY LIMITED31 units
?

Frequently Asked Questions

When is possession of GARDEN AVENUE - K K3?

As per MahaRERA, proposed possession is Dec 2023, revised to Dec 2023.

Is GARDEN AVENUE - K K3 RERA-registered?

Yes β€” MahaRERA registration P99000007110, registered 2021-09-09. No litigations on record.

Who is the developer?

Sridutt Constructions View their track record β–Έ

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Virar West β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
Our advisor replies on WhatsApp within 2 working hours (9am–8pm IST).
βœ“ MahaRERA P52000016540β˜… Featured
The Wadhwa Group
Wadhwa Wise City, New Panvel
1 BHK, 2 BHK, 3 BHK Β· β‚Ή16,946/sq.ft Β· Possession 2026-12-01 00:00:00
Learn more β€Ί

πŸ“° Latest Mumbai Property News

View all news β†’