Possession Timeline
Proposed
Dec 2024
Status
New
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
1 BHK307–411 ft²On request
2 BHK439 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P51700049257
Registered
2025-09-09
Litigation
No reported in source
Escrow Bank
G P PARSIK BANK
Architect
A K & Associates
Total FSI
1831
04
Buildings · 2 Wing(s)
Wing A5 floors · 29 units
Wing B5 floors · 12 units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Kongaon
19.2434177,73.1134296
19.2434177,73.1134296
▸ Explore map & Street View — for verified buyers
07
Promoter & Professionals
AL BRUJ DEVELOPERSNA
A K & ASSOCIATES ARSHAD MOHAMMED SALEEM ANSARIArchitect
09
Construction Progress
100% avgBasement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%
10
Amenities
Electrical Meter Room, Sub-Station, Receiving StationEnergy managemcntEnergy managementFire Protection And Fire Safety RequirementsSewerage (Chamber, Lines, Septic Tank , STP)Street Lighting
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory14
More by Al Bruj Developers
15
MahaRERA projects nearby in Kongaon
?
Frequently Asked Questions
When is possession of Kalyan Aashiyana?
As per MahaRERA, proposed possession is Dec 2024.
Is Kalyan Aashiyana RERA-registered?
Yes — MahaRERA registration P51700049257, registered 2025-09-09. The current MahaRERA source record reports no litigations.
Who is the developer?
Al Bruj Developers — 1945 projects tracked on Mumbai Property Exchange.
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.