R
✓ MahaRERA P51700033506RERA: no litigation reported480
Units
2023
Possession
2
Buildings
Certificate Signed
Status
Lifecycle requires verification
Ask an advisor to verify the current project and inventory status.
Source stage: New · mapped resale: 0 · mapped rental: 0 · primary status: not confirmed
01
Possession Timeline
Proposed
Aug 2023
Status
New
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
1 BHK431 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P51700033506
Registered
2022-02-22
Litigation
No reported in source
Escrow Bank
SARASWAT COOPERATIVE BANK LIMITED
Architect
Vitan Consultants
Total FSI
36904
04
Buildings · 2 Wing(s)
Angelica Building No 2532 floors · — units
Aster Building No 2432 floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Dombivli (East)
▸ Explore map & Street View — for verified buyers
07
Promoter & Professionals
REGENCY NIRMAN LTDNA
Anil Jessaram Bathijadirector
CHIRAG KAILASH AGARWALDIRECTOR
MAHESH SATYANARAYAN KHAIRARIMANAGING DIRECTOR
MAHESH SATYANARAYAN KHAIRARIManaging Director
MANISHA AKASH AGARWALDIRECTOR
Manoj Ramawtar Lalpuriadirector
Niraj Ramakant Sharmadirector
09
Construction Progress
91% avgBasement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%
Podiums (if any) 0%
10
Amenities
Aggregate area of recreational Open SpaceElectrical Meter Room, Sub-Station, Receiving StationEnergy managemcntEnergy managementFire Protection And Fire Safety RequirementsInternal Roads & FootpathsLandscaping & Tree PlantingLandscaping & Tree PlantingSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And DisposalStorm Water DrainsStreet LightingTreatment And Disposal Of Sewage And Sullage WaterWater Conservation, Rain water HarvestingWater SupplyWater conservation /Rain water harvesting
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory08
Property Rates in Dombivli (East)
Residential · Sale
₹10,000–15,000/sqft
Commercial · Sale
₹6,500–10,000/sqft
2 BHK · Rent
₹15,000–35,000/mo
Full rates
14
More by Regency Nirman
15
MahaRERA projects nearby in Dombivli (East)
?
Frequently Asked Questions
When is possession of Regency Anantam Phase V?
As per MahaRERA, proposed possession is Aug 2023.
Is Regency Anantam Phase V RERA-registered?
Yes — MahaRERA registration P51700033506, registered 2022-02-22. The current MahaRERA source record reports no litigations.
Who is the developer?
Regency Nirman — 14 projects tracked on Mumbai Property Exchange. View their track record ▸
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.