S
✓ MahaRERA P51900007789RERA: no litigation reported11
Units
2022
Possession
1
Buildings
Certificate Signed
Status
Lifecycle requires verification
Ask an advisor to verify the current project and inventory status.
Source stage: Ongoing · mapped resale: 0 · mapped rental: 0 · primary status: not confirmed
01
Possession Timeline
Proposed
Dec 2022
Revised
Dec 2022
Status
Ongoing
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
1 BHK371–420 ft²On request
2 BHK605–676 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P51900007789
Registered
2021-09-09
Litigation
No reported in source
Escrow Bank
KOTAK MAHINDRA BANK LIMITED
Architect
Rahul Kamathi
Total FSI
1599
04
Buildings · 1 Wing(s)
Shanti Ashish16 floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Mumbai City
19.021722400000002,72.837479000000002
19.021722400000002,72.837479000000002
▸ Explore map & Street View — for verified buyers
07
Promoter & Professionals
Ruparel Estates India Pvt LtdNA
Mr Rahul Kamathi KamathiArchitect
09
Construction Progress
9% avgExcavation100%
Basement (if any)0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor 0%
10
Amenities
Electrical Meter Room, Sub-Station, Receiving StationFire Protection And Fire Safety RequirementsSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And DisposalStorm Water DrainsWater Conservation, Rain water HarvestingWater SupplyWater conservation /Rain water harvesting
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory14
More by Ruparel Estates India
15
MahaRERA projects nearby in Mumbai City
Daffodil Heights326 unitsSimana - Wing A - Phase 1237 unitsLodha Worli Residential Project195 unitsRunwal Raaya - Tower 1193 unitsNathani Square163 units379 Vista158 units21, Baugh-E-Hasnain134 unitsBafna Pride131 unitsRaheja Sobo Residences129 unitsNebula122 units232 Dhuleva122 units25 Downtown-Wing 1-Emerald Palm114 units
?
Frequently Asked Questions
When is possession of Shaanti Ashish?
As per MahaRERA, proposed possession is Dec 2022, revised to Dec 2022.
Is Shaanti Ashish RERA-registered?
Yes — MahaRERA registration P51900007789, registered 2021-09-09. The current MahaRERA source record reports no litigations.
Who is the developer?
Ruparel Estates India — 34 projects tracked on Mumbai Property Exchange. View their track record ▸
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.