A first look at SM Elite
SM Elite is a residential project by S.M. Hitech in Taloja, Mumbai 410208. It is registered with MahaRERA under P52000052521 (registered 2023-09-08). The project has 194 units across 2 buildings of up to 14 floors. It offers 2 & 3 BHK homes with carpet areas of 522–776 sq ft, priced ₹55.01 Lac–₹87.5 Lac as on 09 Jul 2026 (indicative). The quoted rate is about ₹11,000 per sq ft. MahaRERA proposed possession: Apr 2028.
Ask an advisor to verify current developer inventory and price.
Availability & Pricing
Prices as on 09 Jul 2026. Approximate pricing as on that date. Prices are indicative, subject to change and to reconfirmation with the developer.
💬 Request latest price on WhatsAppUnit configurations filed with MahaRERA (3)
SM Elite floor plans
2Floor plans are indicative, as shared by the developer, and subject to change.
About SM Elite
Location
SM Elite is located in Taloja, Mumbai 410208, in the Raigarh district.
MahaRERA record
The MahaRERA registration number is P52000052521, issued on 8 September 2023. The registered promoter is S M Hitech Developers. The filing lists 2 wings: WING -A with 101 units over 14 floors; WING -B with 93 units over 14 floors. Per the registration, the architect on record is Destination Architecture Interior Design and the project escrow account is with Axis Bank.
Homes and prices
Configurations recorded are 2 BHK of 522–532 sq ft at ₹55.01 Lac–₹57.9 Lac; 3 BHK of 675–776 sq ft at ₹73.7 Lac–₹87.5 Lac (carpet area), as on 09 Jul 2026. That works out to about ₹10,500–₹11,300 per sq ft of carpet. Prices are indicative and should be reconfirmed with the developer before booking.
Construction and possession
The latest MahaRERA progress report shows foundation at 80%, structure at 96%, finishing at 38%, services at 64%. Proposed possession is Apr 2028.
Developer track record
S.M. Hitech has 5998 projects tracked on Mumbai Property Exchange, 5035 of them delivered (ready or sold out). Other projects by the same developer include Prestige Thane, Kanakia Privaasa, Fame Garden.
Buyer demand in Taloja
In the last 90 days, buyers and tenants registered 18 requirements for Taloja with Mumbai Property Exchange, 3 of them to buy and 2 specifically for 2 & 3 BHK homes.
Taloja market
prices, rents & ratesPrice vs locality
Property rates in Taloja
Upcoming projects & infrastructure in Taloja
take an informed decision66 MahaRERA projects are due to hand over in Taloja between 2026 and 2030; the nearest upcoming infrastructure to SM Elite is the Virar-Alibaug Multimodal Corridor, 0.7 km away (approved).
- 🛣️Virar-Alibaug Multimodal CorridorApproved0.7 km
- 🚇Line 12 OrangeUnder construction · due 20261.2 km
Ask on WhatsApp — we answer right in the chat with live asking prices, listings and registered sales for Taloja, then an advisor calls about your budget and configuration.
Prices and timelines are indicative and subject to change. See the disclaimer at the foot of this page.
RERA record & possession
Buildings · 2 wings
194 unitsLocation
Construction progress
per MahaRERASee all 14 stages ▾
What you pay, and when
an exampleThis is just an example of the cash flows for buying a home, not a quote or a payment demand. Your agreement and the developer's schedule decide the actual amounts.
In an under-construction project, you don't pay everything on day one. Under the MahaRERA model agreement, the developer can only ask for money as each stage is finished: about 10% at booking, 30% at agreement, then more as the plinth, slabs, walls, fittings and lifts are done, and the last 5% at possession. The more a building is finished, the more you pay up front.
Example: 3 BHK · 675 sq ft at ₹73.7 L (the price recorded above).
- ✓ Plinth complete45% paid by then
- ✓ Slabs complete70% paid by then
- ○ Walls, plaster & flooring75% paid by then
- ○ Sanitary fittings80% paid by then
- ○ Staircases, lift wells & lobbies85% paid by then
- ○ Lifts, pumps, plumbing & elevation95% paid by then
- ○ Possession100%
With a home loan: banks usually fund up to 75% (₹55.3 L here), released stage by stage, so your own money is about ₹18.4 L plus stamp duty and GST. Until possession you pay interest only on what the bank has released; after that the full EMI is roughly ₹48,000/month (8.5%, 20 years).
Indicative only. Rates, GST (1% on affordable homes), loan eligibility and the stage schedule vary. Plan your cash flow with an advisor before you book.
💬 Talk through the numbers with an MPE advisorAmenities
18+10 more ▾
Next steps — clarity before you step out
Buying a home is not a quick decision. In association with developers, Mumbai Property Exchange sets up the video briefings (Google Meet, Teams or WhatsApp video), the site visits and the paperwork questions — so your homework is done before you commit an afternoon.
More by S.M. Hitech
Compare SM ELITE with similarly priced projects nearby
MahaRERA projects nearby in Taloja
Frequently Asked Questions
Where is SM Elite located?
SM Elite is in Taloja, Mumbai 410208.
What is the price of SM Elite?
2 & 3 BHK homes are priced ₹55.01 Lac–₹87.5 Lac as on 09 Jul 2026, about ₹11,000 per sq ft. Prices are indicative and subject to reconfirmation with the developer.
What configurations and carpet areas does SM Elite offer?
2 BHK – 522 sq ft carpet at ₹55.01 Lac; 2 BHK – 532 sq ft carpet at ₹57.9 Lac; 3 BHK – 675 sq ft carpet at ₹73.7 Lac; 3 BHK – 776 sq ft carpet at ₹87.5 Lac.
When is possession of SM Elite?
As per MahaRERA, proposed possession is Apr 2028.
Is SM Elite RERA-registered?
Yes — MahaRERA registration P52000052521, registered 2023-09-08.
How many units does SM Elite have?
MahaRERA records 194 units across 2 buildings, up to 14 floors.
Who is the developer of SM Elite?
S.M. Hitech — 5998 projects tracked on Mumbai Property Exchange. View their track record ▸
How many new projects are coming up in Taloja?
66 MahaRERA-registered projects in Taloja are due for possession between 2026 and 2030, as per MahaRERA registrations. Timelines can change.
What metro and infrastructure is near SM Elite?
Virar-Alibaug Multimodal Corridor — approved, 0.7 km away; Line 12 Orange — under construction · due 2026, 1.2 km away. Timelines are as announced and can change.
How do I book or get more details?