V
✓ MahaRERA P51800035019RERA: no litigation reportedVivan
Goregaon Electrical Industries
📍 Ram Mandir Goregaon West, Mumbai Suburban · 400104
405
Units
2028
Possession
5
Buildings
Certificate Signed
Status
Primary inventory recorded
Ask an advisor to verify current developer inventory and price.
Source stage: Under Construction · mapped resale: 0 · mapped rental: 0 · primary status: recorded
PB
Pooja Batra · Senior Advisor
Mumbai Property Exchange · MahaRERA-registered since 2017
★
Gallery


₹
Price vs Locality
₹26,212
/sqft · locality avg ₹40,000
₹
Goregaon West — resale, rent & yield
Resale
₹31,325/sqft
median · 63 listings
Rent
₹79.2/sqft/mo
2 BHK ~₹70,000/mo
Gross yield
3.0%/yr
rent vs resale value
This project is quoted around ₹26,212/sqft — 16% below resale here.
From MPE live listings, last 18 months · Mumbai price index ›
01
Possession Timeline
Proposed
Dec 2028
Status
New
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
Shop115 ft²₹30 L
1 BHK300–420 ft²₹79 L–₹1.1 Cr
2 BHK575–599 ft²₹1.51 Cr–₹1.57 Cr
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P51800035019
Registered
2023-11-22
Litigation
No reported in source
Escrow Bank
HDFC BANK
Architect
—
Total FSI
19075
04
Buildings · 5 Wing(s)
Sale Component In Rehab Building25 floors · — units
Wing A26 floors · — units
Wing B26 floors · — units
Wing C26 floors · — units
Wing D26 floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Ram Mandir Goregaon West
19.150291987930764,72.849092001153960
19.150291987930764,72.849092001153960
▸ Explore map & Street View — for verified buyers
07
Promoter & Professionals
GOREGAON ELECTRICAL INDUSTRIES LLPNA
08
Availability & Pricing
TypeCarpetPriceAvail
1 BHK361 ft²₹94.73 Lac—
1 BHK380 ft²₹99.55 Lac—
1 BHK383 ft²₹1 Cr—
2 BHK575 ft²₹1.51 Cr—
2 BHK598 ft²₹1.57 Cr—
09
Construction Progress
76% avgBasement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Slabs of Super Structure100%
Stilt Floor 100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks97%
Sanitary Fittings within the flats / premises90%
Podiums (if any) 80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
10
Amenities
Aggregate area of recreational Open SpaceElectrical Meter Room, Sub-Station, Receiving StationEnergy managemcntEnergy managementFire Protection And Fire Safety RequirementsInternal Roads & FootpathsLandscaping & Tree PlantingLandscaping & Tree PlantingSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And DisposalStorm Water DrainsStreet LightingTreatment And Disposal Of Sewage And Sullage WaterWater Conservation, Rain water HarvestingWater SupplyWater conservation /Rain water harvesting
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory08
Property Rates in Ram Mandir Goregaon West
Residential · Sale
₹35,000–45,000/sqft
Commercial · Sale
₹30,000–45,000/sqft
2 BHK · Rent
₹60,000–120,000/mo
Full rates
09
Resale Flats for Sale in Ram Mandir Goregaon West
410
Flats for Rent in Ram Mandir Goregaon West
411
Commercial for Sale in Ram Mandir Goregaon West
312
Commercial for Lease in Ram Mandir Goregaon West
413
Commercial Projects in Ram Mandir Goregaon West
VS
Compare Vivan with nearby projects
?
Frequently Asked Questions
When is possession of Vivan?
As per MahaRERA, proposed possession is Dec 2028.
Is Vivan RERA-registered?
Yes — MahaRERA registration P51800035019, registered 2023-11-22. The current MahaRERA source record reports no litigations.
What configurations and prices are available?
5 configuration(s), including 1 BHK of 361 sqft at ₹94.73 Lac. See the pricing table above.
Who is the developer?
Goregaon Electrical Industries — 1 projects tracked on Mumbai Property Exchange.
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.