R
✓ MahaRERA P51700008116RERA: no litigation reported192
Units
2019
Possession
1
Buildings
Certificate Signed
Status
Lifecycle requires verification
Ask an advisor to verify the current project and inventory status.
Source stage: Ongoing · mapped resale: 0 · mapped rental: 0 · primary status: not confirmed
01
Possession Timeline
Proposed
Jun 2019
Revised
Jun 2019
Status
Ongoing
02
Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
2 BHK828 ft²On request
3 BHK1,176 ft²On request
Configurations & carpet per MahaRERA filing · indicative price = locality rate × carpet (not the developer's quote).
💬 Verify current inventory with an advisor03
RERA Trust Record
MahaRERA No.
P51700008116
Registered
2017-08-18
Litigation
No reported in source
Escrow Bank
SARASWAT COOPERATIVE BANK LIMITED
Architect
Reza Kabul
Total FSI
21434
04
Buildings · 1 Wing(s)
Type C 228 floors · — units
05
Land DNA · Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold — provenance from MPE's verification layer. The genesis no portal shows.
06
Location
📍 Ulhasnagar
19.248014999999999,73.170764000000005
19.248014999999999,73.170764000000005
▸ Explore map & Street View — for verified buyers
07
Promoter & Professionals
REGENCY NIRMAN LTDNA
Anil Jessaram Bathijadirector
CHIRAG KAILASH AGARWALDIRECTOR
MAHESH SATYANARAYAN KHAIRARIMANAGING DIRECTOR
MAHESH SATYANARAYAN KHAIRARIManaging Director
MANISHA AKASH AGARWALDIRECTOR
Manoj Ramawtar Lalpuriadirector
Niraj Ramakant Sharmadirector
09
Construction Progress
100% avgBasement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%
10
Amenities
Aggregate area of recreational Open SpaceCommunity BuildingsElectrical Meter Room, Sub-Station, Receiving StationEnergy managemcntEnergy managementFire Protection And Fire Safety RequirementsInternal Roads & FootpathsLandscaping & Tree PlantingLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And DisposalStorm Water DrainsStreet LightingTreatment And Disposal Of Sewage And Sullage WaterWater Conservation, Rain water HarvestingWater SupplyWater conservation /Rain water harvesting
12
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Verify current project inventory14
More by Regency Nirman
15
MahaRERA projects nearby in Ulhasnagar
Regency Antilia Phase Viii Avana506 unitsRegency Antilia Phase Ix Avana475 unitsKohinoor Gardens349 unitsGolden City308 unitsCrosstown Ii C Wing307 unitsKohinoor Anaya202 unitsSeagreen Rudra199 unitsPushpraj Prime181 unitsSea Green Aurus142 unitsSunrise Towers124 unitsSharda Royce105 unitsElite Crystal102 units
?
Frequently Asked Questions
When is possession of Regency Antilia Phase - III?
As per MahaRERA, proposed possession is Jun 2019, revised to Jun 2019.
Is Regency Antilia Phase - III RERA-registered?
Yes — MahaRERA registration P51700008116, registered 2017-08-18. The current MahaRERA source record reports no litigations.
Who is the developer?
Regency Nirman — 14 projects tracked on Mumbai Property Exchange. View their track record ▸
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.