Kandivali East · Mumbai
Sethia Aashray
Akurli cross road, Kandivali East · by Sethia Infrastructure (Aakash Developers)
Registered project name
Sethia Aashray - Phase 1Updated Sep 2026
Kandivali EastPhotos from the project record · tap to enlarge
A first look at Sethia Aashray
Sethia Aashray is a residential project on Akurli cross road, Kandivali East, Mumbai 400101. It is registered with MahaRERA under P51800027166 (registered 2025-09-11). Sethia Aashray is sold out by the developer — resale flats here are listed from ₹90 Lac. The project has 115 units across 1 building of up to 25 floors. It offers 1 BHK homes with carpet areas of 321 sq ft. MahaRERA proposed possession: Oct 2027.
1 for sale in this building right now, listed below.
Unit configurations filed with MahaRERA (3)
Property listings in Sethia Aashray
Sethia Aashray floor plans
2Floor plans are indicative, as shared by the developer, and subject to change.
About Sethia Aashray
Location
Sethia Aashray is located on Akurli cross road, Kandivali East (Mumbai 400101), in the Mumbai Suburban district. Across 35 recent resale listings on MPE, homes in Kandivali East have a median asking rate of ₹26,429 per sq ft, and a 2 BHK typically rents for about ₹60,000 a month.
MahaRERA record
Sethia Aashray is registered with MahaRERA under P51800027166, dated 11 September 2025. The registered promoter is Aakash Developers. The filing lists 1 wing: Phase 1 with 115 units over 25 floors. According to MahaRERA, the architect on record is Pankaj Biyani and the project escrow account is with ICICI Bank Ltd.
Homes and prices
Configurations recorded are 1 BHK of 321 sq ft at ₹72.71 Lac (carpet area), as on 09 Jul 2026. That works out to about ₹22,700 per sq ft of carpet, 14% below the locality's resale median. Prices are indicative and should be reconfirmed with the developer before booking.
Construction and possession
The latest MahaRERA progress report shows foundation at 80%, structure at 100%, finishing at 100%, services at 100%. Proposed possession is Oct 2027.
Developer track record
Sethia Infrastructure has 12 projects tracked on Mumbai Property Exchange, 8 of them delivered (ready or sold out). Other projects by the same developer include Golden Jubilee Tower.
Buyer demand in Kandivali East
In the last 90 days, buyers and tenants registered 18 requirements for Kandivali East with Mumbai Property Exchange, 7 of them to buy and 3 specifically for 1 BHK homes.
Developer's description ▾
Kandivali East market
prices, rents & ratesPrice vs locality
Kandivali East — resale, rent & yield
This project is quoted around ₹22,651/sqft — 14% below resale here.
From MPE live listings, last 18 months · Mumbai price index ›
Property rates in Kandivali East
Upcoming projects & infrastructure in Kandivali East
take an informed decision7 MahaRERA projects are due to hand over in Kandivali East between 2026 and 2030; the nearest upcoming infrastructure to Sethia Aashray is the Goregaon-Mulund Link Road (GMLR), 3.0 km away (under construction · due 2028).
Supply is not evenly spread — one year carries almost half of it.
- 🚇Goregaon-Mulund Link Road (GMLR)Under construction · due 20283.0 km
🔒 Units handing over each year · price by BHK · years to absorb supply · competing projects · infra impact on prices
Prices and timelines are indicative and subject to change. See the disclaimer at the foot of this page.
RERA record & possession
Buildings · 1 wing
115 unitsLocation
Construction progress
per MahaRERASee all 11 stages ▾
What you pay, and when
an exampleThis is just an example of the cash flows for buying a home, not a quote or a payment demand. Your agreement and the developer's schedule decide the actual amounts.
In an under-construction project, you don't pay everything on day one. Under the MahaRERA model agreement, the developer can only ask for money as each stage is finished: about 10% at booking, 30% at agreement, then more as the plinth, slabs, walls, fittings and lifts are done, and the last 5% at possession. The more a building is finished, the more you pay up front.
Example: 1 BHK · 321 sq ft at ₹72.7 L (the price recorded above).
- ✓ Plinth complete45% paid by then
- ✓ Slabs complete70% paid by then
- ✓ Walls, plaster & flooring75% paid by then
- ✓ Sanitary fittings80% paid by then
- ✓ Staircases, lift wells & lobbies85% paid by then
- ✓ Lifts, pumps, plumbing & elevation95% paid by then
- ○ Possession100%
With a home loan: banks usually fund up to 75% (₹54.5 L here), released stage by stage, so your own money is about ₹18.2 L plus stamp duty and GST. Until possession you pay interest only on what the bank has released; after that the full EMI is roughly ₹47,300/month (8.5%, 20 years).
Indicative only. Rates, GST (1% on affordable homes), loan eligibility and the stage schedule vary. Plan your cash flow with an advisor before you book.
💬 Talk through the numbers with an MPE advisorAmenities
9+1 more ▾
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Ask about resale or rental optionsResale Flats for Sale in Kandivali East
4Flats for Rent in Kandivali East
4Commercial for Sale in Kandivali East
3Commercial for Lease in Kandivali East
2Commercial Projects in Kandivali East
More by Sethia Infrastructure (Aakash Developers)
MahaRERA projects nearby in Kandivali East
Frequently Asked Questions
Where is Sethia Aashray located?
Sethia Aashray is on Akurli cross road, Kandivali East, Mumbai 400101.
What is the price of Sethia Aashray?
Sethia Aashray is sold out by the developer — resale flats here are listed from ₹90 Lac. These are current asking prices from live listings on MPE.
What configurations and carpet areas does Sethia Aashray offer?
1 BHK – 321 sq ft carpet.
When is possession of Sethia Aashray?
As per MahaRERA, proposed possession is Oct 2027.
Is Sethia Aashray RERA-registered?
Yes — MahaRERA registration P51800027166, registered 2025-09-11.
How many units does Sethia Aashray have?
MahaRERA records 115 units across 3 buildings, up to 25 floors.
Who is the developer of Sethia Aashray?
Sethia Infrastructure (Aakash Developers) — 12 projects tracked on Mumbai Property Exchange. View their track record ▸
How many new projects are coming up in Kandivali East?
7 MahaRERA-registered projects in Kandivali East are due for possession between 2026 and 2030, as per MahaRERA registrations. Timelines can change.
What metro and infrastructure is near Sethia Aashray?
Goregaon-Mulund Link Road (GMLR) — under construction · due 2028, 3.0 km away. Timelines are as announced and can change.
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.


