Kandivali East · Mumbai
Chaitanya Kohinoor
Cross road No. 2, Near Dev-Vrat Tower, Kandivali East · by Chaitanya Group
Updated Sep 2026
Kandivali EastPhotos from the project record · tap to enlarge
A first look at Chaitanya Kohinoor
Chaitanya Kohinoor is a residential project on Cross road No. 2, Near Dev-Vrat Tower, Kandivali East, Mumbai 400101. It is registered with MahaRERA under P51800024570 (registered 2021-09-08). Chaitanya Kohinoor is sold out by the developer; ask MPE for resale or rental flats in this building. The project has 47 units across 1 building of up to 15 floors. It offers 1 & 2 BHK homes with carpet areas of 369–576 sq ft. MahaRERA proposed possession: Jun 2023.
Ask an advisor to check current resale or rental availability.
Unit configurations filed with MahaRERA (3)
Chaitanya Kohinoor floor plans
2Floor plans are indicative, as shared by the developer, and subject to change.
About Chaitanya Kohinoor
Location
Chaitanya Kohinoor is located on Cross road No. 2, Near Dev-Vrat Tower, Kandivali East (Mumbai 400101), in the Mumbai Suburban district. Across 35 recent resale listings on MPE, homes in Kandivali East have a median asking rate of ₹26,429 per sq ft, and a 2 BHK typically rents for about ₹60,000 a month.
MahaRERA record
The MahaRERA registration number is P51800024570, issued on 8 September 2021. The registered promoter is Chaitanya Developers. The filing lists 1 wing: CHAITANYA KOHINOOR over 15 floors. Per the registration, the architect on record is Rasik P Hingoo Associates and the project escrow account is with Punjab National Bank.
Homes and prices
Configurations recorded are 1 BHK of 369 sq ft at ₹1.12 Cr; 2 BHK of 576 sq ft at ₹1.75 Cr (carpet area), as on 09 Jul 2026. That works out to about ₹30,400 per sq ft of carpet, 15% above the locality's resale median. Prices are indicative and should be reconfirmed with the developer before booking.
Construction and possession
The latest MahaRERA progress report shows foundation at 80%, structure at 100%, finishing at 100%, services at 100%. Proposed possession is Jun 2023.
Developer track record
Chaitanya Group has 20 projects tracked on Mumbai Property Exchange, 18 of them delivered (ready or sold out). Other projects by the same developer include Ethics Oliver , Ganapati Baug CHSL, Chaitanya Om Shivam.
Buyer demand in Kandivali East
In the last 90 days, buyers and tenants registered 18 requirements for Kandivali East with Mumbai Property Exchange, 7 of them to buy and 6 specifically for 1 & 2 BHK homes.
Developer's description ▾
Kandivali East market
prices, rents & ratesPrice vs locality
Kandivali East — resale, rent & yield
This project is quoted around ₹30,367/sqft — 15% above resale here.
From MPE live listings, last 18 months · Mumbai price index ›
Property rates in Kandivali East
Upcoming projects & infrastructure in Kandivali East
take an informed decision7 MahaRERA projects are due to hand over in Kandivali East between 2026 and 2030.
Supply is not evenly spread — one year carries almost half of it.
🔒 Units handing over each year · price by BHK · years to absorb supply · competing projects · infra impact on prices
Prices and timelines are indicative and subject to change. See the disclaimer at the foot of this page.
RERA record & possession
Buildings · 1 wing
Location
Construction progress
per MahaRERASee all 11 stages ▾
What you pay, and when
an exampleThis is just an example of the cash flows for buying a home, not a quote or a payment demand. Your agreement and the developer's schedule decide the actual amounts.
In an under-construction project, you don't pay everything on day one. Under the MahaRERA model agreement, the developer can only ask for money as each stage is finished: about 10% at booking, 30% at agreement, then more as the plinth, slabs, walls, fittings and lifts are done, and the last 5% at possession. The more a building is finished, the more you pay up front.
Example: 2 BHK · 576 sq ft at ₹1.75 Cr (the price recorded above).
- ✓ Plinth complete45% paid by then
- ✓ Slabs complete70% paid by then
- ✓ Walls, plaster & flooring75% paid by then
- ✓ Sanitary fittings80% paid by then
- ✓ Staircases, lift wells & lobbies85% paid by then
- ✓ Lifts, pumps, plumbing & elevation95% paid by then
- ○ Possession100%
With a home loan: banks usually fund up to 75% (₹1.31 Cr here), released stage by stage, so your own money is about ₹43.8 L plus stamp duty and GST. Until possession you pay interest only on what the bank has released; after that the full EMI is roughly ₹1.14 L/month (8.5%, 20 years).
Indicative only. Rates, GST (1% on affordable homes), loan eligibility and the stage schedule vary. Plan your cash flow with an advisor before you book.
💬 Talk through the numbers with an MPE advisorAmenities
10+2 more ▾
Talk to our MahaRERA advisor
Tell our MahaRERA advisor what you need and they'll guide you on this project.
💬 Ask about resale or rental optionsResale Flats for Sale in Kandivali East
4Flats for Rent in Kandivali East
4Commercial for Sale in Kandivali East
3Commercial for Lease in Kandivali East
2Commercial Projects in Kandivali East
More by Chaitanya Group
MahaRERA projects nearby in Kandivali East
Frequently Asked Questions
Where is Chaitanya Kohinoor located?
Chaitanya Kohinoor is on Cross road No. 2, Near Dev-Vrat Tower, Kandivali East, Mumbai 400101.
What is the price of Chaitanya Kohinoor?
Chaitanya Kohinoor is sold out by the developer; ask MPE for resale or rental flats in this building.
What configurations and carpet areas does Chaitanya Kohinoor offer?
1 BHK – 369 sq ft carpet; 2 BHK – 576 sq ft carpet.
When is possession of Chaitanya Kohinoor?
As per MahaRERA, proposed possession is Jun 2023.
Is Chaitanya Kohinoor RERA-registered?
Yes — MahaRERA registration P51800024570, registered 2021-09-08.
How many units does Chaitanya Kohinoor have?
MahaRERA records 47 units across 6 buildings, up to 15 floors.
Who is the developer of Chaitanya Kohinoor?
Chaitanya Group — 20 projects tracked on Mumbai Property Exchange. View their track record ▸
How many new projects are coming up in Kandivali East?
7 MahaRERA-registered projects in Kandivali East are due for possession between 2026 and 2030, as per MahaRERA registrations. Timelines can change.
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.