Basement (if any)100%
Plinth100%
Podiums (if any) 100%
Slabs of Super Structure100%
Stilt Floor 100%
Excavation96%
Slabs of Super Structure84%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.16%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises9%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.8%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Sanitary Fittings within the flats / premises0%