Kandivali West · Mumbai
Shree Gopaldham
Kandivali West · by JE & VEE Infrastructure
Updated Oct 2026
Kandivali WestPhotos from the project record · tap to enlarge

A first look at Shree Gopaldham
Shree Gopaldham is a residential project by JE & VEE Infrastructure in Kandivali West, Mumbai 400067. It is registered with MahaRERA under P51800079265 (registered 2025-02-25). It offers 2, 3 & 4 BHK homes with carpet areas of 801–1,883 sq ft, priced ₹2.9 Cr–₹6.59 Cr as on 09 Jul 2026 (indicative). The quoted rate is about ₹36,000 per sq ft. MahaRERA proposed possession: Apr 2031.
Ask an advisor to verify current developer inventory and price.
Availability & Pricing
Prices as on 09 Jul 2026. Approximate pricing as on that date. Prices are indicative, subject to change and to reconfirmation with the developer.
💬 Request latest price on WhatsAppShree Gopaldham floor plans
1Floor plans are indicative, as shared by the developer, and subject to change.
About Shree Gopaldham
Location
The project is in Kandivali West, Mumbai 400067, in the Mumbai Suburban district. Across 335 recent resale listings on MPE, homes in Kandivali West have a median asking rate of ₹29,900 per sq ft, and a 2 BHK typically rents for about ₹55,000 a month.
MahaRERA record
Shree Gopaldham is registered with MahaRERA under P51800079265, dated 25 February 2025. The registered promoter is Je And Vee Infrastructure. The filing lists 1 wing: 1 over 3 floors. According to MahaRERA, the architect on record is Three Dimensional Consultantllp and the project escrow account is with ICICI Bank Ltd.
Homes and prices
Configurations recorded are 2 BHK of 801 sq ft at ₹2.9 Cr; 3 BHK of 1,152–1,477 sq ft at ₹4.09 Cr–₹5.2 Cr; 4 BHK of 1,883 sq ft at ₹6.59 Cr (carpet area), as on 09 Jul 2026. That works out to about ₹35,000–₹36,200 per sq ft of carpet, 19% above the locality's resale median. Prices are indicative and should be reconfirmed with the developer before booking.
Construction and possession
MahaRERA progress reports show construction has not started yet on any of the 11 tracked stages. Proposed possession is Apr 2031.
Developer track record
JE & VEE Infrastructure has 170 projects tracked on Mumbai Property Exchange, 135 of them delivered (ready or sold out). Other projects by the same developer include Codename A-One, Rustomjee Ozone Skye, Modi Arcade.
Buyer demand in Kandivali West
In the last 90 days, buyers and tenants registered 45 requirements for Kandivali West with Mumbai Property Exchange, 21 of them to buy and 14 specifically for 2, 3 & 4 BHK homes.
Developer's description ▾
Kandivali West market
prices, rents & ratesPrice vs locality
Kandivali West — resale, rent & yield
This project is quoted around ₹36,000/sqft — 20% above resale here.
From MPE live listings, last 18 months · Mumbai price index ›
Property rates in Kandivali West
Upcoming projects & infrastructure in Kandivali West
take an informed decision82 MahaRERA projects are due to hand over in Kandivali West between 2026 and 2030; the nearest upcoming infrastructure to Shree Gopaldham is the Borivali-Thane Tunnel, 3.0 km away (under construction · due 2028).
Supply is not evenly spread — one year carries about a third of it.
- 🚇Borivali-Thane TunnelUnder construction · due 20283.0 km
Ask on WhatsApp — we answer right in the chat with live asking prices, listings and registered sales for Kandivali West, then an advisor calls about your budget and configuration.
Prices and timelines are indicative and subject to change. See the disclaimer at the foot of this page.
RERA record & possession
Buildings · 1 wing
Location
Construction progress
per MahaRERASee all 11 stages ▾
What you pay, and when
an exampleThis is just an example of the cash flows for buying a home, not a quote or a payment demand. Your agreement and the developer's schedule decide the actual amounts.
In an under-construction project, you don't pay everything on day one. Under the MahaRERA model agreement, the developer can only ask for money as each stage is finished: about 10% at booking, 30% at agreement, then more as the plinth, slabs, walls, fittings and lifts are done, and the last 5% at possession. The more a building is finished, the more you pay up front.
Example: 3 BHK · 1477 sq ft at ₹5.20 Cr (the price recorded above).
- ○ Plinth complete45% paid by then
- ○ Slabs complete70% paid by then
- ○ Walls, plaster & flooring75% paid by then
- ○ Sanitary fittings80% paid by then
- ○ Staircases, lift wells & lobbies85% paid by then
- ○ Lifts, pumps, plumbing & elevation95% paid by then
- ○ Possession100%
With a home loan: banks usually fund up to 75% (₹3.90 Cr here), released stage by stage, so your own money is about ₹1.30 Cr plus stamp duty and GST. Until possession you pay interest only on what the bank has released; after that the full EMI is roughly ₹3.38 L/month (8.5%, 20 years).
Indicative only. Rates, GST (1% on affordable homes), loan eligibility and the stage schedule vary. Plan your cash flow with an advisor before you book.
💬 Talk through the numbers with an MPE advisorAmenities
16+8 more ▾
Next steps — clarity before you step out
Buying a home is not a quick decision. In association with developers, Mumbai Property Exchange sets up the video briefings (Google Meet, Teams or WhatsApp video), the site visits and the paperwork questions — so your homework is done before you commit an afternoon.
Resale Flats for Sale in Kandivali West
3Flats for Rent in Kandivali West
3Commercial for Sale in Kandivali West
2Commercial for Lease in Kandivali West
1Commercial Projects in Kandivali West
More by JE & VEE Infrastructure
Compare Shree Gopaldham with similarly priced projects nearby
MahaRERA projects nearby in Kandivali West
Frequently Asked Questions
Where is Shree Gopaldham located?
Shree Gopaldham is in Kandivali West, Mumbai 400067.
What is the price of Shree Gopaldham?
2, 3 & 4 BHK homes are priced ₹2.9 Cr–₹6.59 Cr as on 09 Jul 2026, about ₹36,000 per sq ft. Prices are indicative and subject to reconfirmation with the developer.
What configurations and carpet areas does Shree Gopaldham offer?
2 BHK – 801 sq ft carpet at ₹2.9 Cr; 3 BHK – 1,152 sq ft carpet at ₹4.09 Cr; 3 BHK – 1,477 sq ft carpet at ₹5.2 Cr; 4 BHK – 1,883 sq ft carpet at ₹6.59 Cr.
When is possession of Shree Gopaldham?
As per MahaRERA, proposed possession is Apr 2031.
Is Shree Gopaldham RERA-registered?
Yes — MahaRERA registration P51800079265, registered 2025-02-25.
Who is the developer of Shree Gopaldham?
JE & VEE Infrastructure — 170 projects tracked on Mumbai Property Exchange. View their track record ▸
How many new projects are coming up in Kandivali West?
82 MahaRERA-registered projects in Kandivali West are due for possession between 2026 and 2030, as per MahaRERA registrations. Timelines can change.
What metro and infrastructure is near Shree Gopaldham?
Borivali-Thane Tunnel — under construction · due 2028, 3.0 km away. Timelines are as announced and can change.
How do I book or get more details?
Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor — serving Mumbai since 1995 · RERA-registered since 2017.