List PropertyWhatsApp
New ProjectsBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your PropertyπŸ’¬ WhatsApp Us
πŸ† Mumbai's oldest property portalSince 1995βœ“ MahaRERA A51800043517βœ“ RERA-verified project data🟒 We reply in minutes on WhatsApp
R
βœ“ MahaRERA P99000018043βœ“ Clear

Rustomjee Virar Avenue D1 Wing A And Wing B And Retail Building by Keystone Infrastructure

πŸ“ Avenue D1, Palghar Β· 401303
236
Units
2021
Possession
3
Buildings
Certificate Signed
Status
01Possession Timeline
Proposed
Dec 2021
Status
New
02Unit Configurations (per MahaRERA)
ConfigurationCarpetIndicative Price
1 BHK331 ftΒ²On request
2 BHK472–512 ftΒ²On request
First Floor1,349 ftΒ²On request
Ground Floor2,462 ftΒ²On request
Configurations & carpet per MahaRERA filing Β· indicative price = locality rate Γ— carpet (not the developer's quote).
πŸ’¬ Live availability, floor plans & today's price β€” on WhatsApp
03RERA Trust Record
MahaRERA No.
P99000018043
Registered
2021-09-09
Litigation
None on record
Escrow Bank
ICICI BANK LIMITED
Architect
Abhikalpan Architects & Planners
Total FSI
10086
04Buildings Β· 3 Wing(s)
Retail Building3 floors Β· β€” units
Wing A17 floors Β· β€” units
Wing B17 floors Β· β€” units
05Land DNA Β· Genesis
Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06Location
πŸ“ Avenue D1
19.471155728288290,72.801738950537130
β–Έ Explore map & Street View β€” for verified buyers
07Promoter & Professionals
VINCENT PATRICK RODRIGUESDirector
09Construction Progress100% avg
Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Plinth100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
10Amenities
Aggregate area of recreational Open SpaceBox Cricket on Podium TopDG back up for elevators and common area lightingDesigner Entrance lobbyElectrical Meter Room, Sub-Station, Receiving StationFire Protection And Fire Safety RequirementsFutsal CourtJogging Track on podium topLandscaping & Tree PlantingMultipurpose lawn on podium topOrganic Waste Converter for recycle of wet garbageSewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsWater Conservation, Rain water HarvestingWater Supplychildren play area with rubber mat and play equippment on podium topcommon area fire sprinklerscommon area lightingearthquake resistent structureelevatorspodium parkingsenior citizen plaza with reflexology pathskating area on podium topsolar systemstaircase and liftlobbies
12Floor Plans, E-Brochure & Payment Plans
πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13EMI Calculator
β€”
?Frequently Asked Questions
When is possession of RUSTOMJEE VIRAR AVENUE D1 WING A AND WING B AND RETAIL BUILDING?

As per MahaRERA, proposed possession is Dec 2021.

Is RUSTOMJEE VIRAR AVENUE D1 WING A AND WING B AND RETAIL BUILDING RERA-registered?

Yes β€” MahaRERA registration P99000018043, registered 2021-09-09. No litigations on record.

Who is the developer?

Keystone Infrastructure β€” 5 projects tracked on Mumbai Property Exchange. View their track record β–Έ

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Avenue D1 β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
βœ“ MahaRERA P51700077356β˜… Featured
Lodha Group
Lodha Hanging Gardens, Dombivli
3 BHK, 4 BHK Β· β‚Ή16,400/sq.ft Β· Possession Dec 2027
Learn more β€Ί

πŸ“° Latest Mumbai Property News

View all news β†’